35-BM Beamline Operations

Control of 35-BM shutter operation has been turned over to the 35-BM (ASD) staff and the main control room (MCR) operators (ASD-OA). The MCR has full operation of the beam-line shutter controls, and also the permit to allow shutter enable for the 35-BM beamline.

All other aspects of FC responsibilities are the same for the 35-BM beamline as for any other beamline. The contact point is the ASD beamline staff when present or the MCR operators.

Author: Bruce Glagola,   Nena Moonier, reviewed 1/8/2019