EFO Group Instructions for Operators

This web page contains information for the MCR Operators regarding off hours responses to 0101 requests.
InstructionsDescriptionReview DatePowerPoint Presentation
Posting EA/EHCP Forms

MCR Operators are not allowed to post ESAFs.

If you get a call in the off-shift to post an ESAF, please let the user know you are not allowed to post an ESAF and the posting and start of the experiment will have to wait until the on-duty Floor Coordinator arrives at 0800 the following morning.

02/21/26 
FE-EPS Reset

Instructions on how to reset trips of the Front-End Equipment Protection System.

NOTE: If there is a FEEPS fault, but no page from beamline personnel or user regarding the fault, then no action is required at that time.

 

02/21/26 
PSS Trip ResetInstructions on how to reset Trips of the Personnel Safety System02/21/26 
Global Offline

Instructions on how to place beamlines in Global Offline state.

NOTE: MCR operators are only allowed to place beamlines Globally Offline after being authorized to do so by the on-duty Floor Coordinator. All steps of the Offline portion of the procedure MUST be followed. 

02/21/26 
Securing Hazardous SamplesInstructions on securing experimental enclosures which contain hazardous samples02/21/26 
Enclosure ODH AlarmPolicy and Procedure: Enclosure ODH Alarm02/21/26 
Miscellaneous RequestsInstructions for miscellaneous requests to 2-010101/30/18