The Advanced Photon Source
a U.S. Department of Energy Office of Science User Facility

Long Beamline Building Construction Schedule

Project Manager: Steve Hunsberger (847-975-9428)
APS Point-of Contact: Mohan Ramanathan (630-822-5625)
Contractor: Power Construction

The Long Beamline Building (LBB) Construction is scheduled to start on October 26, 2020.  The project's initial activity is the chain link fence installation, which will continue through November 6, 2020. 

This construction schedule web page will be updated every two weeks.

For activities related to LBB contruction a mailman server has been initiated. The messages posted to the sever can be obtained at:
https://mailman-int.aps.anl.gov/pipermail/lbb_construction_info

LBB Construction Schedule
Date Construction Activity Expected Vibration Level 
(Low, Moderate, High)
May 17 Detail Steel HEXM Low
May 18 Detail Steel HEXM, Hoist Mechanical Equipment to Mezz (EH) Low
May 19 Detail Steel HEXM, Place Basement Concrete, Hoist Mechanical Equipment to Mezz (EH) Low
May 20 Detail Steel HEXM, Detail Steel ISN, Place Basement Concrete, Hoist Mechanical Equipment to Mezz (EH) Low
May 21 Detail Steel HEXM, Detail Steel ISN, CMU Walls, Install New Door Frame (EH), Metal Roof Decking Low
May 24 Detail Steel ISN, CMU Walls, Install New Door Frame (EH), Patch Walls (EH), Metal Roof Decking Low
May 25 Detail Steel ISN, CMU Walls, Patch Walls (EH), Metal Roof Decking Low
May 26 Detail Steel ISN, CMU Walls, Patch Walls (EH), Metal Roof Decking Low
May 27 CMU Walls, Patch Walls (EH), Metal Roof Decking Low
March 28 CMU Walls, Patch Walls (EH), Metal Roof Decking Low

Schedule subject weather conditions

 

05.17.2021