Electrical Upgrade, New ComEd Feed to ANL

  • Project Manager: Jon Cisek
  • Engineer: Dan Nassar for ANL Utilities/George Doktorczyk for APS Site Operations
  • APS AES + MCR: John Connolly / Randy Flood
  • Contractor: Meade Electric

Note: Electrical service interruption to the APS is NOT expected as a result of this project.

Phase 1: Meade has confirmed that they are on schedule to complete bus 1 replacement at 549 during the spring APS shutdown, specifically April 24-May 8, with clean power to APS by May 13.

Phase 2: Meade will also complete the 549 bus 2 replacement during the APS fall shutdown, specifically August 22-September 12, with clean power to APS by September 16.