27-ID and 35-ID

Installation schedule for the sector 27 Control room.

Status
  • Receive materials on Friday March 10, 2014
  • Installation starts on Monday March 10, 2014
  • Installation of control room walls and decking complete on March 24,2014
  • 2" D.I. water mains to run on roof decking of control room, then tie-in to existing 1" water drops going into 27-ID-A and 27-ID-B hutches. installation to start March 24,2014 – Completed no later than May 2, 2014
  • HVAC rough-in March 24,2014 - March 28, 2014
  • Sprinkler rough-in March 24,2014-March 28,2014
  • Electrical, Data, Fire, Smoke, EM lighting rough-in March 28,2014 – April 21,2014
  • Installation dropped ceiling April 21,2014 – April 23,2014
  • HVAC trim out supply and returns April 24,2014 – May 2, 2014
  • Sprinklers trim out April 24,2014 - May 2,2014
  • Electrical trim outlets, install lighting, trim out fire & smoke alarms, data April 24,2014 – May 2, 2014
  • Beneficial Occupancy and generation of Punch list May 5, 2014