- Receive materials on Friday March 10, 2014
- Installation starts on Monday March 10, 2014
- Installation of control room walls and decking complete on March 24,2014
- 2" D.I. water mains to run on roof decking of control room, then tie-in to existing 1" water drops going into 27-ID-A and 27-ID-B hutches. installation to start March 24,2014 – Completed no later than May 2, 2014
- HVAC rough-in March 24,2014 - March 28, 2014
- Sprinkler rough-in March 24,2014-March 28,2014
- Electrical, Data, Fire, Smoke, EM lighting rough-in March 28,2014 – April 21,2014
- Installation dropped ceiling April 21,2014 – April 23,2014
- HVAC trim out supply and returns April 24,2014 – May 2, 2014
- Sprinklers trim out April 24,2014 - May 2,2014
- Electrical trim outlets, install lighting, trim out fire & smoke alarms, data April 24,2014 – May 2, 2014
- Beneficial Occupancy and generation of Punch list May 5, 2014
|