Hi,
The number of PV is not the problem... we are using this IOC to forward PV along with a very precise time scheduler to other IOC synchronized with the White Rabbit protocol. Therefore I need to handle network latency to get the minimun delay, check that all PVs have arrived to all IOCs before the time that they were scheduled, etc... And this was not possible with the PVGateway or sequencer. but thanks to the examples that Tim suggested me and by looking at the nice presentation http://www.aps.anl.gov/bcda/ I could make the CA work by
I still need to do more tests but I think that I am making progress.... thank you anyway for your suggestion. Best, On Tue, Apr 11, 2017 at 7:12 PM, Mark S. Engbretson <[email protected]> wrote:
| ||||||||||||||||