Subject: RE: Status of devlib2 project?
From: "Williams Jr., Ernest L." <[email protected]>
To: Andrew Johnson <[email protected]>, Michael Davidsaver <[email protected]>
Cc: "[email protected]" <[email protected]>, "Luchini, Kristi L." <[email protected]>, "Straumann, Till" <[email protected]>, "Kim, Kukhee" <[email protected]>, "Brown, Garth" <[email protected]>
Date: Wed, 21 May 2014 08:44:44 -0700
Hi Andrew
________________________________________
From: Andrew Johnson [[email protected]]
Sent: Wednesday, May 21, 2014 8:06 AM
To: Williams Jr., Ernest L.; Michael Davidsaver
Cc: [email protected]; Luchini, Kristi L.; Brown, Garth; Kim, Kukhee; Straumann, Till
Subject: Re: Status of devlib2 project?

Hi Ernest,

On 05/21/2014 08:08 AM, Williams Jr., Ernest L. wrote:
>
> Hopefully, we can work on the above now or at the next codeathon. :)

I'm going to predict that Michael will probably have fixed the problem
before then.

====
====
Awesome :)

> We are planning to use EPICS 3.15.x and some EPICS Version 4 services for the new LCLS 2
> control system.

Do you have any timescales for that project? ITER have a requirement for
a 3.15.1 release by the end of this year, but despite my asking nobody
else has *ever* given me specific dates from other projects.

=== 
===
Our time scale for 3.15.1 would be around Spring 2015.
We could possibly use it according to ITER's schedule as well.
Parts of LCLS 2 controls will be worked on by partner labs and some early
prototyping and R&D will begin getting underway in October 2014.

Some key areas:
(1) The new event/timing system we must design for LCLS 2
(2) Beam Synchronous Acquisition (Jeff Hill calls it Flavored-Data at LANSCE)
(3) Loading/Unloading records dynamically ?
(4) Support for hot-swapping


> I have not checked as of yet but does devlib2 make its way into 3.15 ?

That is the purpose of the merge request that we're been linking to and
discussing.

==
== 
Sounds good.


- Andrew

--
Advertising may be described as the science of arresting the human
intelligence long enough to get money from it. -- Stephen Leacock


References:
Status of devlib2 project? Williams Jr., Ernest L.
Re: Status of devlib2 project? Michael Davidsaver
Re: Status of devlib2 project? Andrew Johnson
RE: Status of devlib2 project? Williams Jr., Ernest L.
Re: Status of devlib2 project? Andrew Johnson

Navigate by Date:
Prev: Re: Status of devlib2 project? Andrew Johnson
Next: [Merge] lp:~epics-core/epics-base/spinlockfix into lp:epics-base mdavidsaver
Index: 2002  2003  2004  2005  2006  2007  2008  2009  2010  2011  2012  2013  <20142015  2016  2017  2018  2019  2020  2021  2022  2023  2024 
Navigate by Thread:
Prev: Re: Status of devlib2 project? Andrew Johnson
Next: RE: Status of devlib2 project? Williams Jr., Ernest L.
Index: 2002  2003  2004  2005  2006  2007  2008  2009  2010  2011  2012  2013  <20142015  2016  2017  2018  2019  2020  2021  2022  2023  2024 
ANJ, 27 May 2014 Valid HTML 4.01! · Home · News · About · Base · Modules · Extensions · Distributions · Download ·
· Search · EPICS V4 · IRMIS · Talk · Bugs · Documents · Links · Licensing ·