Subject: RE: Release Timetable for R3.14.12.2
From: Di Maio Franck <[email protected]>
To: Andrew Johnson <[email protected]>
Cc: EPICS core-talk <[email protected]>, Zagar Anze EXT <[email protected]>, Makijarvi Petri <[email protected]>
Date: Tue, 25 Oct 2011 09:12:49 +0200
Thanks, Andrew, for this schedule synchronization.
These dates would be perfect for us.
We'll run tests on RHEL 6 (64 bits) as the 1st priority, then on RHEL 6.1-MRG.
We'll coordinate with you for the test suite.
Franck

Franck Di Maio
CODAC System Designer
CODAC Section

ITER Organization, Building 519/027, CHD, Control System Division
Route de Vinon sur Verdon - 13115 St Paul Lez Durance - France
Phone: +33 4 42 17 64 05

-----Original Message-----
From: Andrew Johnson [mailto:[email protected]] 
Sent: 24 October 2011 23:56
To: EPICS core-talk
Cc: Di Maio Franck
Subject: Release Timetable for R3.14.12.2

ITER have asked if we can produce a 3.14.12.2 release of Base in time for them to include it in their CODAC Core System version 3.0.  The dates below were picked with the ITER calendar in mind (and also fit in with the APS winter shutdown, which is convenient), although Franck hasn't yet responded to my email presenting these dates to him so he might want some changes.

      ...      Fix known bugs
  2011-Nov-14  Publish R3.14.12.2-pre1
      ...      Developer Testing
  2011-Nov-28  Publish R3.14.12.2-rc1
      ...      Community Testing
  2011-Dec-05  Publish additional -rc2 release if needed
  2011-Dec-12  Publish additional -rc3 release if needed
  2011-Dec-12  Earliest date to release 3.14.12.2
  2011-Dec-19  Latest date to release 3.14.12.2

This allows 3 weeks for us to fix known bugs before the -pre1 release, and 4 or 5 weeks thereafter for testing, documentation updates and any additional fixes.  Note that the US Thanksgiving holiday falls towards the end of the Developer Testing period, so I hope we'll be able to concentrate most of our testing in the first week.

Since this is a patch release and we haven't included any significant new functionality in the 3.14 branch since 3.14.12, I don't foresee there being any major issues to deal with, although we do have a few bugs that should be fixed if possible before the release.

Core Developers: please check your calendars and respond with any questions or problems you'll have about meeting this timetable.

Thanks,

- Andrew
--
Optimization is the process of taking something that works and replacing it with something that almost works, but costs less.
-- Roger Needham


References:
Release Timetable for R3.14.12.2 Andrew Johnson

Navigate by Date:
Prev: Release Timetable for R3.14.12.2 Andrew Johnson
Next: Reminder: 1 week to R3.14.12.2-pre1 Andrew Johnson
Index: 2002  2003  2004  2005  2006  2007  2008  2009  2010  <20112012  2013  2014  2015  2016  2017  2018  2019  2020  2021  2022  2023  2024 
Navigate by Thread:
Prev: Release Timetable for R3.14.12.2 Andrew Johnson
Next: Reminder: 1 week to R3.14.12.2-pre1 Andrew Johnson
Index: 2002  2003  2004  2005  2006  2007  2008  2009  2010  <20112012  2013  2014  2015  2016  2017  2018  2019  2020  2021  2022  2023  2024 
ANJ, 02 Feb 2012 Valid HTML 4.01! · Home · News · About · Base · Modules · Extensions · Distributions · Download ·
· Search · EPICS V4 · IRMIS · Talk · Bugs · Documents · Links · Licensing ·