I would like to be able to publish a 3.14.12 pre-release version of Base
before the BNL EPICS meeting, which means on October 8th. Allowing an extra
week for -pre testing because of the meeting, that puts the -RC1 on the 22nd,
and the earliest date for the final release would be October 29th.
Does anybody have any problems with this time-scale?
We have already committed almost all of the Codeathon branches for 3.14.12
that I discussed back in June, with the exception of the alarm-filter branch;
if Eric and/or Bernd Schoeneburg would like to review that branch we still
have time left to merge it.
I have been looking through the open bugs and trying to clean up/close out
those that I know we've already fixed or that aren't fixable, but I could use
some help with this.
Any other issues?
- Andrew
--
The best FOSS code is written to be read by other humans -- Harald Welte
- Navigate by Date:
- Prev:
[Merge] lp:~epics-core/epics-base/apple-ios into lp:epics-base noreply
- Next:
Re: alarm acknowledge Andrew Johnson
- Index:
2002
2003
2004
2005
2006
2007
2008
2009
<2010>
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
- Navigate by Thread:
- Prev:
Re: Channel Access and Virtual IPs Ralph Lange
- Next:
Re: alarm acknowledge Andrew Johnson
- Index:
2002
2003
2004
2005
2006
2007
2008
2009
<2010>
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
|