APS Beamline Commissioning Activity Approval Form


Sequence No : 33-ID-07-20
Sector : 33 Beamline : ID
Start Date : 19 Oct 2007 Duration : 2 weeks
Date and Time of Submission : 10-19-07 09:33

Commissioning Envelope :
The maximum operating current is 100 mA ma
The minimum ID gap is 11 mm mm
Modes : White beam where allowed by configuration

Activity Description:
Commission re-configured beam line. First bring light into 33ID-C, then validate shielding. Once shielding survey is satisfactory, PSL monochromator will be re-commissioned. Subsequently, the newly installed Kohzu monochromator will commissioned.

Commissioning Team Members

First and Last Name AffiliationPhone Number
1. Paul Zschack XOR 2-0860
2. Zhan Zhang XOR 2-0863
3. Jenia Karapetrova XOR 2-0865
4. Oliver Schmidt AES

Special Safety Concerns:
Repositioned and newly installed critical components must be positioned correctly on the beam line and determined to operate as designed.

Submitted by Commissioning Activity Team Leader:
Name : Paul Zschack Date : 10-19-07
E-Mail : zschack@anl.gov

ADD for Operations Comment :
Valid for 2 weeks. Beamline to be disabled on 9 Nov 2007 unless other authorization is provided. Inform AES-ADD/MIS office of survey results.
Approved by ADD for Ops./Designee : John Quintana on 10-25-07