APS Beamline Commissioning Activity Approval Form


Sequence No : 32-ID-07-8
Sector : 32 Beamline : ID
Start Date : 02/01/2006 Duration : 1 month
Date and Time of Submission : 02-01-07 11:50

Commissioning Envelope :
The maximum operating current is 100 ma
The minimum ID gap is 11 mm
Modes : White and Mono Beam

Activity Description:
Verification of the 32-ID-B Backstop at a 25mm gap and then an 11mm gap.

Commissioning Team Members

First and Last Name AffiliationPhone Number
1. Mohan Ramanathan AES-MIS 822-5625
2. Mark Erdman AES-MED 252-7282
3. Wah-Keat Lee XSD-XIS 252-7759
4. Cindy Chaffee AES-UES 252-0300
5. John Vacca ESH-HP 252-6180
6. Rod Salazar AES-MIS 252-9495

Special Safety Concerns:
Station C will not be enabled.

Submitted by Commissioning Activity Team Leader:
Name : Cindy Chaffee Date : 02-01-07
E-Mail : cchaffee@aps.anl.gov

ADD for Operations Comment :
None
Approved by ADD for Ops./Designee : John Quintana on 02-02-07