APS Beamline Commissioning Activity Approval Form


Sequence No : 14-ID-06-20
Sector : 14 Beamline : ID
Start Date : 10/17/2006 Duration : 2hours
Date and Time of Submission : 10-16-06 14:14

Commissioning Envelope :
The maximum operating current is 51. ma
The minimum ID gap is 11. mm
Modes : white beam in A,B,C

Activity Description:
Shielding Re-Verification of 14-ID-B at 50mA. One water-cooled Al scatterring target located upstream of the station. All RSS components verified and tagged.

Commissioning Team Members

First and Last Name AffiliationPhone Number
1. Tim Graber CARS-CAT 2-0462
2. Patti Pedergnana APS 2-0401
3. Kevin Randall APS 2-8446
4. Mohan Ramanathan APS 2-3773
5. Harold Brewer CARS-CAT 2-0447
6. Rod Salazar APS 2--9495

Special Safety Concerns:
RSS components verified and tagged. Ozone mitigation: station fan turned on and monitor in place near entrance to the station.

Submitted by Commissioning Activity Team Leader:
Name : salazar Date : 10-16-06
E-Mail :

ADD for Operations Comment :
ozone mitigation for window and station
Approved by ADD for Ops./Designee : on 10-17-06