CAT Chat Minutes

November 19, 2007

Operations Update, Mark Beno

Problems:

  • Real time feedback
  • Under 100MA

Stats:

  • 99.5% - Beamtime
  • 120 hours – Meantime between faults

Safety, Paul Rossi

An independent assessment for laser users will be conducted by EQO. Assessment criteria will be distributed.

In February a site wide ISMS assessment will be conducted. This assessment will consist of 20 DOE assessors and will take place in a two-week period. An ISM day will probably be conducted prior to the ISMS assessment.

Questions/Comments, Mark Beno

Beam motion startup problems should be brought to Glenn Decker.

Next Meeting:

The next CAT Chat meeting will be held on November 26, 2007.

Happy Thanksgiving!!