Special Operating Modes for Operating Cycle 1998-4
This schedule is current as of September 3, 1998 @ 13:15
| Special Operating Modes(SOM)
(includes Shielding Verification (SV) and Shielding Verification Shedule) |
|||
| Date | Time | Activity | Other Information |
| Mon., Aug. 10, 1998 | COB | Requests for SOM | Deadline for requests for SOM for Oct. thru Dec. (1998-5) Operating Cycle |
| Tues., Aug. 11, 1998 | 0800 | SV |
|
| Tues., Aug. 18, 1998 | 0800 | SV |
|
| Tues., Sept. 22, 1998 | 0800 | SOM |
|
| Wed., Sept. 23, 1998 | Continued | SOM |
|
| Thur., Sept. 24, 1998 | Continued | SOM |
|
| Fri., Sept. 25, 1998 | Continued | SOM |
|
| Sat., Sept. 26, 1998 | Continued | SOM |
|
| Sun., Sept. 27, 1998 | Ending 0800 | SOM |
|
| Parasitic Schedule | ||
| Parasitic Shielding Schedule (TBD upon 48 hrs . notice from CAT) | ||
|
||