Special Operating Modes for Operating Cycle 1998-3
This schedule is current as of June 29, 1998 @ 13:40
| Special Operating Modes(SOM)
(includes Shielding Verification (SV) and Shielding Verification Shedule) |
|||
| Date | Time | Activity | Other Information |
| Tues., May 26, 1998 | COB | Requests for SOM | Deadline for requests for SOM for Aug/Sept (1998-4) Operating Cycle |
| Tues., May 26, 1998 | 0800 | SV- Operating Current 25 mA |
|
| Tues., June 16, 1998 | 0800 | SV - Operating Current 10 - 25 mA |
|
| Tues., June 30, 1998 | 0800 | SV - Operating Current 10 - 25 mA |
|
| Tues., July 7, 1998 | 0800 | SVC |
|
| Following SV | SOM |
|
|
| Wed., July 8, 1998 | Continued | SOM |
|
| Thur., July 9, 1998 | Continued | SOM |
|
| Fri., July 10, 1998 | Continued | SOM |
|
| Sat., July 11, 1998 | Continued | SOM |
|
| Sun., July 12, 1998 | Ending 2400 | SOM |
|
| Parasitic Schedule | ||
| Parasitic Shielding Schedule (TBD upon 48 hrs . notice from CAT) | ||
|
|
|
|
|
|