Special Operating Modes for Operating Cycle 1998-3
This schedule is current as of June 29, 1998 @ 13:40

Special Operating Modes(SOM)

(includes Shielding Verification (SV) and Shielding Verification Shedule)

Date Time Activity Other Information
Tues., May 26, 1998 COB Requests for SOM Deadline for requests for SOM for Aug/Sept (1998-4) Operating Cycle
Tues., May 26, 1998 0800 SV- Operating Current 25 mA
  • 9 ID A
  • 20 BM A
Tues., June 16, 1998 0800 SV - Operating Current 10 - 25 mA
  • 15 ID A
Tues., June 30, 1998 0800 SV - Operating Current 10 - 25 mA
  • 33 BM A and B
Tues., July 7, 1998 0800 SVC
  • TBD
Following SV SOM
  • Singlets
Wed., July 8, 1998 Continued SOM
  • Singlets
Thur., July 9, 1998 Continued SOM
  • Singlets
Fri., July 10, 1998 Continued SOM
  • Singlets
Sat., July 11, 1998 Continued SOM
  • Singlets
Sun., July 12, 1998 Ending 2400 SOM
  • Singlets

 

Parasitic Schedule
Parasitic Shielding Schedule (TBD upon 48 hrs . notice from CAT)
  • 33 ID A (May 18, 1998)
  • 1 ID A(May 18, 1998)
  • 5 ID C Backwall
  • 3 ID A (May 18, 1998)
  • 2 ID E and D