APS Long Range Commissioning Schedule for FY1996
Date |
First Shift 0:00-8:00 |
Second Shift 8:00-16:00 |
Third Shift 16:00-24:00 |
| 3/15/96 | SR Studies | 1-ID-A Shielding Verification | SR Studies |
| 3/23/96 | SR Studies | 3-ID-A , 2-ID-A , 3-ID-B Shielding Verifications | User Beam |
| 3/24/96 | User Beam | User Beam | User Beam |
| 3/25/96 | User Beam | 19-ID-A Shielding Verification | User Beam |
| 3/26/96 | User Beam | 2-ID-A , 12-BM-A Shielding Verifications | User Beam |
| 3/27/96 | User Beam | 5-BM-A Shielding Verification | User Beam |
| 3/28/96 | User Beam | 19-ID-C Shielding Verification | User Beam until 20:00 |
| 3/29/96 | SR Studies | SR Studies | SR Studies |
| 3/30/96 | SR Studies | SR Studies | SR Studies |
| 3/31/96 | SR Studies | SR Studies | SR Studies |
| 4/1/96 | SR Studies | SR Studies | SR Studies |
| 4/2/96 | SR Studies | 5-BM-B Shielding Verification | User Beam |
| 4/3/96 | User Beam | User Beam | User Beam |
| 4/4/96 | User Beam | User Beam | User Beam |
| 4/5/96 | User Beam | 19-ID-D Shielding Verification | User Beam |
| 4/6/96 | User Beam | XBPM Studies/User Beam | SR Studies |
| 4/7/96 | SR Studies | SR Studies | SR Studies |
| 4/8/96 | SR Studies | Shutdown | Shutdown |
Date |
First Shift 0:00-8:00 |
Second Shift 8:00-16:00 |
Third Shift 16:00-24:00 |
| 5/3/96 | SR Studies | SR Studies | SR Studies |
| 5/4/96 | SR Studies | SR Studies | SR Studies |
| 5/5/96 | SR Studies | SR Studies | SR Studies |
| 5/6/96 | SR Studies | User Beam | User Beam |
| 5/7/96 | User Beam | 19-ID-D Shielding Verification | User Beam |
| 5/8/96 | User Beam | User Beam | User Beam |
| 5/9/96 | User Beam | User Beam | User Beam |
| 5/10/96 | User Beam | User Beam | User Beam |
| 5/11/96 | User Beam | User Beam | User Beam |
| 5/12/96 | User Beam | User Beam | User Beam |
| 5/13/96 | User Beam | SR Studies | SR Studies |
| 5/14/96 | SR Studies | SR Studies | SR Studies |
| 5/14/96 | SR Studies | SR Studies | SR Studies |
| 5/15/96 | SR Studies | SR Studies | SR Studies |
| 5/16/96 | SR Studies | SR Studies | SR Studies |
| 5/17/96 | SR Studies | SR Studies | SR Studies |
| 5/18/96 | SR Studies | SR Studies | SR Studies |
| 5/19/96 | SR Studies | SR Studies | SR Studies |
| 5/20/96 | SR Studies | 12-ID-A Shielding Verification | User Beam |
| 5/21/96 | User Beam | User Beam | User Beam |
| 5/22/96 | User Beam | 5-ID-A Shielding Verification | User Beam |
| 5/23/96 | User Beam | User Beam | User Beam |
| 5/24/96 | User Beam | 2-BM-A Shielding Verification | User Beam |
| 5/25/96 | User Beam | Shutdown Starts | - |
Date |
First Shift 0:00-8:00 |
Second Shift 8:00-16:00 |
Third Shift 16:00-24:00 |
| 6/18/96 | - | SR Studies | SR Studies |
| 6/19/96 | SR Studies | SR Studies | SR Studies |
| 6/20/96 | SR Studies | SR Studies | SR Studies |
| 6/21/96 | SR Studies | SR Studies | SR Studies |
| 6/22/96 | SR Studies | User Beam / Re-check Shielding of 1-BM-B,12-BM-A,5-BM-A | User Beam |
| 6/23/96 | User Beam | User Beam | User Beam |
| 6/24/96 | User Beam | 2-BM-A Shielding Verification | User Beam |
| 6/25/96 | User Beam | 19-BM-A Shielding Verification | User Beam |
| 6/26/96 | User Beam | User Beam / Re-check Shielding of 5-BM-B | User Beam |
| 6/27/96 | User Beam | User Beam / Re-check Shielding of 5-ID-A | User Beam |
| 6/28/96 | User Beam | User Beam | User Beam |
| 6/29/96 | User Beam | SR Studies | SR Studies |
| 6/30/96 | SR Studies | SR Studies | SR Studies |
| 7/1/96 | SR Studies | SR Studies | SR Studies |
| 7/2/96 | SR Studies | 19-BM-C & D Shielding Verification | User Beam |
| 7/3/96 | User Beam | 33-ID-A Shielding Verification | User Beam |
| 7/4/96 | User Beam | User Beam | User Beam |
| 7/5/96 | User Beam | 17-ID-A Shielding Verification | User Beam |
| 7/6/96 | User Beam | User Beam | User Beam |
| 7/7/96 | User Beam | User Beam until 20:00 | SR Studies |
| 7/8/96 | SR Studies | SR Studies | SR Studies |
| 7/9/96 | SR Studies | Begin Shutdown | - |
Date |
First Shift 0:00-8:00 |
Second Shift 8:00-16:00 |
Third Shift 16:00-24:00 |
| 7/30/96 | Shutdown | Startup | SR Studies |
| 7/31/96 | SR Studies | SR Studies | SR Studies |
| 8/1/96 | SR Studies | SR Studies | SR Studies |
| 8/2/96 | SR Studies | SR Studies | SR Studies |
| 8/3/96 | SR Studies | SR Studies | SR Studies |
| 8/4/96 | SR Studies | SR Studies | SR Studies |
| 8/5/96 | SR Studies | User Beam | User Beam |
| 8/6/96 | User Beam | User Beam | User Beam |
| 8/7/96 | User Beam | User Beam | User Beam |
| 8/8/96 | User Beam | 10-ID-A & 19-BM-D Shielding Verification | Shielding Verification continues til 2000 hrs if needed / User Beam |
| 8/9/96 | User Beam | 19-BM-C Shielding Verification | Shielding Verification continues til 2000 hrs if needed / User Beam |
| 8/10/96 | User Beam | User Beam | User Beam |
| 8/11/96 | User Beam | User Beam | User Beam |
| 8/12/96 | User Beam | User Beam | User Beam |
| 8/13/96 | User Beam | SR Studies | SR Studies til 2000 hrs then User Beam |
| 8/14/96 | User Beam | 33-ID-A & 17-ID-A Shielding Verification | Shielding Verification continues til 2000 hrs if needed then User Beam |
| 8/15/96 | User Beam | 8-ID-A , 19-BM-A & 7-ID-A Shielding Verification | Shielding Verification continues til 2000 hrs if needed then User Beam |
| 8/16/96 | User Beam | 13-BM-A & 7-ID- B Shielding Verification | Shielding Verification continues til 2000 hrs if needed then User Beam |
| 8/17/96 | User Beam | User Beam | User Beam |
| 8/18/96 | User Beam | User Beam | User Beam |
| 8/19/96 | SR Studies | SR Studies | SR Studies |
| 8/20/96 | SR Studies | Begin Shutdown | Shutdown |
Date |
First Shift 0:00-8:00 |
Second Shift 8:00-16:00 |
Third Shift 16:00-24:00 |
| 9/10/96 | Shutdown | Startup | SR Studies |
| 9/11/96 | SR Studies | SR Studies | SR Studies |
| 9/12/96 | SR Studies | SR Studies | SR Studies |
| 9/13/96 | SR Studies | SR Studies | SR Studies |
| 9/14/96 | SR Studies | SR Studies | SR Studies |
| 9/15/96 | SR Studies | SR Studies | SR Studies |
| 8/16/96 | SR Studies | SR Studies | SR Studies |
| 9/17/96 | SR Studies | 13-BM-A Shielding Verification. 0800-1200 User beam @ ~ 30 mA | Shielding Verification continues until 2000 hrs if needed / User Beam |
| 9/18/96 | User Beam | 7-ID-A & B Shielding Verification | Shielding Verification continues until 2000 hrs if needed / User Beam |
| 9/19/96 | User Beam | 17-ID-A Shielding Verification | Shielding Verification continues until 2000 hrs if needed / User Beam |
| 9/20/96 | User Beam | Tours from 0900-1500 hrs | User Beam |
| 9/21/96 | User Beam | Open House 0800-1730 hrs | User Beam |
| 9/22/96 | User Beam | User Beam | User Beam |
| 9/23/96 | User Beam | SR Studies until 2000 hrs then User Beam | User Beam |
| 9/24/96 | User Beam | 33-ID-C Shielding Verification | Shielding Verification continues until 2000 hrs if needed / User Beam |
| 9/25/96 | User Beam | 8-ID-A Shielding Verification | Shielding Verification continues until 2000 hrs if needed / User Beam |
| 9/26/96 | User Beam | 10-ID-A Shielding Verification | Shielding Verification continues until 2000 hrs if needed / User Beam |
| 9/27/96 | User Beam | 13-ID-A Shielding Verification | Shielding Verification continues until 2000 hrs if needed / User Beam |
| 9/28/96 | User Beam | User Beam | User Beam |
| 9/29/96 | User Beam | User Beam | User Beam |
| 9/30/96 | User Beam | Shielding Verification Contingency | User Beam |
| 10/1/96 | User Beam | SR Studies | SR Studies |
| 10/2/96 | SR Studies | SR Studies | SR Studies |
| 10/3/96 | SR Studies | SR Studies | SR Studies |
| 10/4/96 | SR Studies | SR Studies | SR Studies |
| 10/5/96 | SR Studies | SR Studies | SR Studies |
| 10/6/96 | SR Studies | SR Studies | SR Studies |
| 10/7/96 | SR Studies | 0800-1200 User beam @ ~ 30 mA followed by regular User Beam | User Beam |
| 10/8/96 | User Beam | User Beam | User Beam |
| 10/9/96 | User Beam | User Beam | User Beam |
| 10/10/96 | User Beam | User Beam | User Beam |
| 10/11/96 | User Beam | User Beam | User Beam |
| 10/12/96 | User Beam | User Beam | User Beam |
| 10/13/96 | User Beam | User Beam | User Beam |
| 10/14/96 | User Beam | 17-BM-A Shielding Verification | Shielding Verification continues until 2000 hrs if needed / User Beam |
| 10/15/96 | User Beam | 7-ID-A & B Shielding Verification | Shielding Verification continues until 2000 hrs if needed / User Beam |
| 10/16/96 | User Beam | 8-ID-A and 10-ID-A Shielding Verification | Shielding Verification continues until 2000 hrs if needed / User Beam |
| 10/17/96 | User Beam | 5-ID-A Shielding Verification | Shielding Verification continues until 2000 hrs if needed / User Beam |
| 10/18/96 | User Beam | 17-BM-B & Transports Shielding Verification | User Beam |
| 10/19/96 | User Beam | User Beam | User Beam |
| 10/20/96 | User Beam | SR Studies | SR Studies |
| 10/21/96 | SR Studies | SR Studies | SR Studies |
| 10/22/96 | SR Studies | Begin Shutdown | Shutdown |
Date |
First Shift 0:00-8:00 |
Second Shift 8:00-16:00 |
Third Shift 16:00-24:00 |
| 12/3/96 | Shutdown | Startup | SR Studies |
| 12/4/96 | SR Studies | SR Studies | SR Studies |
| 12/5/96 | SR Studies | SR Studies | SR Studies |
| 12/6/96 | SR Studies | SR Studies | SR Studies |
| 12/7/96 | SR Studies | SR Studies | SR Studies |
| 12/8/96 | SR Studies | SR Studies | SR Studies |
| 12/9/96 | SR Studies | SR Studies | SR Studies |
| 12/10/96 | SR Studies | User Operations ( Parasitic Shielding Verification) 1-ID-A , 1-BM-A, 5-BM-A, 2-ID-A |
User Operations |
| 12/11/96 | User Operations | Shielding Verification 8-ID-A, 17-BM-B , 19-ID-C & A | Shielding Verification continues until 2400 hrs if needed / User Operations |
| 12/12/96 | User Operations | Shielding Verification 13-ID-A, 13-BM-A & 12-ID-A |
Shielding Verification continues until 2400 hrs if needed / User Operations |
| 12/13/96 | User operations | User Operations changed to SR Studies | User Operations changed to SR Studies |
| 12/14/96 | User Operations changed to SR Studies | User Operations changed to SR Studies | User Operations changed to SR Studies |
| 12/15/96 | User Operations changed to SR Studies | User Operations changed to SR Studies | User Operations |
| 12/16/96 | User Operations | User Operations ( Parasitic Shielding Verification) 2-ID-E, 17-BM-A, 12-BM-A and 2-ID-D |
User Operations |
| 12/17/96 | User Operations | User Operations | User Operations |
| 12/18/96 | UserOperations | Shielding Verification 20-ID-A*, 19-BM-C and 5-ID-A | Shielding Verification continues until 2000 hrs if needed / User Operations |
| 12/19/96 | User Operations | Shielding Verification 17-ID-A, 10-ID-A and 7-ID-A | Shielding Verification continues until 2000 hrs if needed / User Operations |
| 12/20/96 | User Operations | Shielding Verification 33-ID-C and 7-ID-B | Shielding Verification continues until 2000 hrs if needed / User Operations |
| 12/21/96 | User Operations | User Operations | User Operations |
| 12/22/96 | User Operations | User Operations | User Operations |
| 12/23/96 | User Operations | Begin Maintenance | Maintenance |
- During Shielding Verification, User Operation is permissible once the orbit for the new beamline has been established.
- User Operations = Fill ~ 100 mA ( refill @ 40 mA).
- Shielding Verification = 20 mA ( * = 5 mA also ).
- Stations listed during User Operations time will be verified parasitically under normal operating conditions.