Injector Studies 

Nov. 4th, 0800 - Nov. 16th, 0800

 

Wednesday, 11/04/09

Time
Description
Studiers
Comments


0745-0800

SR Fill  324 Singlets  Non Top-Up


OPS



0800-1200


RG2 Kicker Validation


S. Pasky




1300-1500


Refresh Linac SF6 in Zones B and C.


W. Michalek


Linac RF systems L1 - L3
should be shutdown!
WR26389


1100-1900


L4 RF Conditioning


OPS


Rf conditioning progress to be recorded in operation on-line log
.
Suggested Procedure provided by CO..


1900-2000


Injector Recovery / SR Fill


OPS


324 Singlets


2000-2400


L4 RF Conditioning


OPS


Rf conditioning progress to be recorded in operation on-line log
.
SLOWLY!!!!

Thursday, 11/05/09

Time
Description
Studiers
Comment


0000- 0700


L4 RF Conditioning


OPS


Rf conditioning progress to be recorded in operation on-line log
.
SLOWLY!!!! (Goal 138MW SLED)If this power is reached
attempt operating L5 down L4 providing 325MeV. Save File


0700-0800


Injector Recovery/SR Fill


OPS 


324 Singlets


0900-1100


Console Test  (Booster)


D.Weyer




1100-1500


Linac/Par Studies


S. Pasky/R.Soliday


PEMtool Testing


1500-1900


L5 RF Conditioning


OPS


Rf conditioning progress to be recorded in operation on-line log.
Suggested Procedure provided by CO, pay close attention to L5:BL:VP:CO3.


1900-2000


Injector Recovery/SR Fill


OPS 


324 Singlets


2000-2400


L5 RF Conditioning


OPS


Rf conditioning progress to be recorded in operation on-line log
.
SLOWLY!!!! 

Friday, 11/06/09

Time
Description
Studiers
Comments


0000 - 0500


L5 RF Conditioning


OPS


Rf conditioning progress to be recorded in operation on-line log
.
SLOWLY!!!!(Goal 138MW SLED)If rf power is reached
attempt operating L4 down L5 providing 325MeV. Save File


0500-0700


Restore Normal operations using RG2.

OPS



0700-0800


Injector Recovery/SR Fill


OPS 


324 Singlets


0800-1200


Test Sequence Program


A. Pietryla




1200-1900


L5 RF Conditioning


OPS


Continue to operator L5 SLED at a higher power level
~ (70MW). Setup L4 power to maintain the required 325Mev.


1900-2000


Injector Recovery/SR Fill


OPS 


324 Singlets


2000-2400


Setup Normal operations using RG1.*

(Do not standardize LTP/PAR/PTB
or change Par RF)


OPS


Use LPL_Configure PEMtool.
*Deselect linac L4 and L5 rf systems and LTP, PAR, PTB
Restore "Sys. Ref. High Charge RG1->PAR->BS 325MeV"
Observe gun startup - this is a new cathode - the final gun charge
will be 250ma.

Saturday, 11/07/09

Time
Description
Studiers
Comments


0000-0700


  RG1 operation continued ..........


OPS


Check transport efficiency to the booster.
Save file.


0700-0800


Injector Recovery/SR Fill


OPS 


324 Singlets

0800-1030


"Operators Challenge"


OPS


Operators challenge to perform manual LTP
steering. ACO setup and monitor -

  1. Disable LTP control-law
  2. Move all LTP correctors
  3. Challenger - 
    1. Save file w/challengers name
    2. Manual steer
    3. When good transport is established
    4.  Save file


1200-1900


L5 RF Conditioning


OPS


Continue to operator L5 SLED at a higher power level
~ (70MW). Setup L4 power to maintain the required 325Mev.


1900-2000


Injector Recovery/SR Fill 


OPS


324 Singlets

2000-0000


"Operators Challenge"


OPS


Operators challenge each other by creating faults that are to be diagnosed and discovered.

Sunday, 11/08/09

Time
Description
Studiers
Comments


0000-0200


Setup K2 down using RG1.*

(Do not standardize Linac/LTP/PAR/PTB
or change Par RF)


OPS


Use LPL_Configure PEMtool.
*Deselect linac L4 and L5, rf systems.
Restore "Sys. Ref. High Charge RG1->PAR->BS 325MeV"


0200-0700


Continued K2 down using RG1.*


OPS


Check transport efficiency to the booster.
Save file.


0700-0800


Injector Recovery/SR Fill. 


OPS


324 Singlets


0800-1100


Restore Normal operations using RG2.

OPS

Use LPL_Configure PEMtool.
*Deselect linac L4 and L5, rf systems when using
Sys. Ref. High Charge RG2->PAR->BS 325MeV
or operator preferred.


1200-1500


Setup K2 down using RG2.*

(Do not standardize Linac/LTP/PAR/PTB
or change Par RF)


OPS


Use LPL_Configure PEMtool.
*Deselect linac L4 and L5, rf systems when using
 Sys. Ref. K2 Down RG2->PAR->BS 325 MeV.


1600-1900


Restore Normal operations using RG2.

OPS

Use LPL_Configure PEMtool.
*Deselect linac L4 and L5, rf systems when using
Sys. Ref. High Charge RG2->PAR->BS 325MeV
or operator preferred.


1900-2000


Injector Recovery/SR Fill.


OPS


324 Singlets

2000-2400


"Operators Challenge"


OPS


Operators challenge each other by creating faults that are to be diagnosed and discovered.

Monday, 11/09/09

Time
Description
Studiers
Comments

0000-0700


"Operators Challenge"


OPS


Operators challenge each other by creating faults that are to be diagnosed and discovered.


0700-0800


Injector Recovery/SR Fill. 


OPS


324 Singlets


0800-1200


Test Sequence Program


A. Pietryla




1200-1500


Linac/Par Beam Studies


S.Pasky




1900-2000


Injector Recovery/SR Fill.


OPS


324 Singlets


2000 - 0000


L5 RF Conditioning


OPS


Rf conditioning progress to be recorded in operation on-line log
.
SLOWLY!!!!(Goal 138MW SLED)If rf power is reached
attempt operating L4 down L5 providing 325MeV. Save File

Tuesday, 11/10/09

Time
Description
Studiers
Comments

0000-0200


L5 RF Conditioning


OPS


Rf conditioning progress to be recorded in operation on-line log
.
SLOWLY!!!!(Goal 138MW SLED)If rf power is reached
attempt operating L4 down L5 providing 325MeV. Save File

0200-0800


Restore L4 and L5 RF SLED power to 40MW each.


OPS


Verify beam transport to booster and
save files...


0800 -

Machine Studies Period

Wednesday, 11/11/09

Time
Description
Studiers
Comments

0000-0700








0700-0800


Injector Recovery/SR Fill. 


OPS


324 Singlets


0800-1200


Interface L1:CM1 and CM2


A. Pietryla/C.Gold
/R.Keane/S.Pasky

Investigate timing issues with L1:CM1 and L1:CM2
Current monitiors. L1:CM1 will not work properly without
someone changing the timing on the local DG-535.


1200-1500


Linac/Par/Booster Beam Studies


S.Pasky




1500-1700


Restore Normal operations using RG2.

OPS



1700-2000


Injector Recovery/SR Fill.


OPS


324 Singlets


2000-2400


Setup Normal operations using RG1.*

(Do not standardize LTP/PAR/PTB
or change Par RF)


OPS


Use LPL_Configure PEMtool.
*Deselect linac L4 and L5, rf systems!!!!.
Restore "Sys. Ref. High Charge RG1->PAR->BS 325MeV"

Thursday, 11/12/09

Time
Description
Studiers
Comments


0000-0700


  RG1 operation continued ..........


OPS


Check transport efficiency to the booster.
Save file.


0700-0800


Injector Recovery/SR Fill. 


OPS


324 Singlets


0800-1400


RG1 Kicker Validation


S. Pasky




1400-1600


Linac RF Souce Maintenance


A. Grelick, D. Jefferson


Adjust the amplitude from the 119 MHz Linac Source
chassis to match that from the synthesizer source.

Note -
shutdown all linac klystrons while doing this.


1700-2000


Injector Recovery/SR Fill.


OPS


324 Singlets


2000-0000


Restore Normal operations using RG2.

OPS

Use LPL_Configure PEMtool.
*Deselect linac L4 and L5, rf systems when using
Sys. Ref. High Charge RG2->PAR->BS 325MeV
or operator preferred.

Friday, 11/13/09

Time
Description
Studiers
Comments

0000-0200


continued - Normal operations using RG2


OPS




0700-0800


Injector Recovery/SR Fill. 


OPS


324 Singlets


0900-1200


Booster Injection Kicker Testing


A. Hillman /S.Pasky


Correlate dropouts in BTS charge with the booster injection kicker


1200-1900


L5 RF Conditioning


OPS


Operator L5 SLED at a higher power level
~ (70MW). Setup L4 power to maintain the required 325Mev.


1900-2000


Injector Recovery/SR Fill.


OPS


324 Singlets


2000-2400


Setup Normal operations using RG1.*

(Do not standardize LTP/PAR/PTB
or change Par RF)


OPS


Use LPL_Configure PEMtool.
*Deselect linac L4 and L5 rf systems and LTP, PAR, PTB
Restore "Sys. Ref. High Charge RG1->PAR->BS 325MeV"
Observe gun startup - this is a new cathode - the final gun charge
will be 250ma.

Saturday, 11/14/09

Time
Description
Studiers
Comments


0000-0700


  RG1 operation continued ..........


OPS


Check transport efficiency to the booster.
Save file.


0700-0800


Injector Recovery/SR Fill. 


OPS


324 Singlets

0800-1030


"Operators Challenge"


OPS


Operators challenge to perform manual LTP
steering. ACO setup and monitor -

  1. Disable LTP control-law
  2. Move all LTP correctors
  3. Challenger - 
    1. Save file w/challengers name
    2. Manual steer
    3. When good transport is established
    4.  Save file


1200-1900


L5 RF Conditioning


OPS


Operator L5 SLED at a higher power level
~ (70MW). Setup L4 power to maintain the required 325Mev.


1900-2000


Injector Recovery/SR Fill.


OPS


324 Singlets

2000-2400


L5 RF Conditioning


OPS


Continue to operator L5 SLED at a higher power level
~ (70MW). Setup L4 power to maintain the required 325Mev.

Sunday, 11/15/09

Time
Description
Studiers
Comments

0000-0700


L5 RF Conditioning


OPS


Continue to operator L5 SLED at a higher power level
~ (70MW). Setup L4 power to maintain the required 325Mev.


0700-0800


Injector Recovery/SR Fill. 


OPS


324 Singlets


0800-1100


Restore Normal operations using RG2.

OPS

Use LPL_Configure PEMtool.
*Deselect linac L4 and L5, rf systems when using
Sys. Ref. High Charge RG2->PAR->BS 325MeV
or operator preferred.

1100-1900


L5 RF Conditioning


OPS


Continue to operator L5 SLED at a higher power level
~ (70MW). Setup L4 power to maintain the required 325Mev.


1900-2000


Injector Recovery/SR Fill.


OPS


324 Singlets

2000-2400


Restore L4 and L5 RF SLED power to 40MW each.


OPS


Verify beam transport to booster and
save files...

Monday, 11/16/09


0000-0800


Maintain Normal operations using RG2.

OPS



0800 -

Machine Studies Period