Machine Start Up

Draft Schedule for Run06-1, 2016



Time

Descriptions

Work lead

Comments


Tuesday January 12, 2016 - Tuesday January 19, 2016



1600-2400

Linac RF conditioning

Ops


0600

Open Linac tunnel

Ops



Tuesday January 19, 2016



1700-1800

Booster magnet ramp tests

Yao, Xu

Booster in Authroized Access Doors Locked






Wednesday, January 20, 2016




Final network work

IT

Must be done prior to 08:00

0600-1000

IOC & timing system checkout

Controls


0800-1000

Final walkthroughs


All technical groups

1000-1200

Secure tunnels

Ops


1200

Restore timing parameters

Ops

After CTLs work

1300-1400

Rack in switchgear for all machines

FMS

After Ops secures tunnels

1400-1500

ACIS shutdown validations

Ops, RF,PS

Injectors only

1500-2400

RF conditioning

RF/Ops

RF may want to bypass MPS interface

1500-1900

SCU measurements

MED

Access Zone A

1500-2400

PS testing

PS group



ACIS “live tests”

Ops

As appropriate


Thursday, January 21, 2016



0000-2400

RF conditioning

RF/Ops

RF may want to bypass MPS interface

0000-2400

PS testing

PS group



ACIS “live tests”

Ops

As appropriate





0900

Rack in 13.2kV switchgear

FMS Linesmen/OPS

RF-1 not racked in. Key to procedural control

0930-1030

Shutdown validations of SRRF and S:BM

Ops, RF, PS



Monday, January 25, 2016



0700-0800

MPS validations

CTLS/Ops

Coordinate with RF group

1000-2400

SR RF Conditioning w/ beam

Ops