Machine Start Up

Draft Schedule for Run05-2, 2015



Time

Descriptions

Work lead

Comments


Thursday, May 14, 2015







1300-1500

Final walkthroughs Zone F


All technical groups

1500-1600

Secure Zone F

Ops



Friday, May 15, 2015




Contingency plan. Schedule starting on Monday may shift to today to support SCU1




Final network work (Zone F)

IT

Must be done prior to 08:00

0800-0900

Rack in 13.2kV switchgear

FMS Linesmen/OPS


0900-1000

SRRF ACIS shutdown validations

Ops, RF

Except for SR dipole

1000-2400

RF conditioning

RF/Ops

RF may want to bypass MPS interface










Monday, May 18, 2015




Final network work

IT

Must be done prior to 08:00

0800-1000

Final walkthroughs


All technical groups

0800-1200

IOC & timing system checkout

Controls


1030-1230

Secure Tunnels

Ops


1100-1300

Rack in switchgear for all machines

FMS

After Ops secures tunnels

1200

Restore timing parameters

Ops

After CTLs work





1200-1400

ACIS shutdown validations

Ops, RF, PS groups


1300-2400

PS testing

PS group


4 hours

(1300-1700)

ID testing

Grimmer

May allow parasitic PS testing


ACIS “live tests”

Ops

As appropriate


Tuesday, May 19, 2015



0000-2400

RF conditioning

RF/Ops

RF may want to bypass MPS interface

0000-2400

PS testing

PS group


1100-1130

SR ACIS shutdown validations

Ops/ PS



ACIS “live tests”

Ops

As appropriate

0000-2400

RF conditioning

RF/Ops

RF may want to bypass MPS interface

0000-2400

PS testing

PS group



Wednesday, May 20, 2015



0000-2400

RF conditioning

RF/Ops

RF may want to bypass MPS interface

0000-2400

PS testing

PS group



ACIS “live tests”

Ops

As appropriate














Thursday, May 21, 2015



0700-0800

MPS validations

CTLS/Ops

Coordinate with RF group

0800-1000

BPLD validations

Bui


1000-2400

SR RF Conditioning w/ beam

Ops