Machine Start Up

Draft Schedule for Run03-3, 2014



Time

Descriptions

Work lead

Comments


Thursday, September 18, 2014




Final network work

IT

Must be done prior to 08:00

0800-1000

Final walkthroughs


All technical groups

0800-1200

IOC & timing system checkout

Controls


1030-1230

Secure All Tunnels

Ops


1100-1300

Rack in switchgear for all machines

FMS

After Ops secures tunnels

1200

Restore timing parameters

Ops

After CTLs work

1130 - 1200

Rack in 13.2kV switchgear

FMS Linesmen/OPS


1200-1400

ACIS shutdown validations

Ops, RF, PS groups


1300-2400

RF conditioning

RF/Ops

RF may want to bypass MPS interface

1300-2400

PS testing

PS group


4 hours

(1300-1700)

ID testing

Grimmer

May allow parasitic PS testing


ACIS “live tests”

Ops

As appropriate






Wednesday, September 24, 2014



0700-0800

MPS validations

CTLS/Ops

Coordinate with RF group

0800-2400

SR RF Conditioning w/ beam

Ops