Machine Start Up

Draft Schedule for Run05-3, 2015



Time

Descriptions

Work lead

Comments


Tuesday, September 22, 2015




Final network work

IT

Must be done prior to 08:00

0600-1000

IOC & timing system checkout

Controls


0800-1000

Final walkthroughs


All technical groups

1000-1200

Secure tunnels

Ops


1200

Restore timing parameters

Ops

After CTLs work

1300-1400

Rack in switchgear for all machines

FMS

After Ops secures tunnels

1300-1400

Rack in 13.2kV switchgear

FMS Linesmen/OPS


1400-1500

ACIS shutdown validations

Ops, RF


1500-2400

RF conditioning

RF/Ops

RF may want to bypass MPS interface

1500-2400

PS testing

PS group



ACIS “live tests”

Ops

As appropriate


Wednesday, September 23, 2015



0000-2400

RF conditioning

RF/Ops

RF may want to bypass MPS interface

0000-2400

PS testing

PS group



Thursday, September 24, 2015



0000-2400

RF conditioning

RF/Ops

RF may want to bypass MPS interface

0000-2400

PS testing

PS group



ACIS “live tests”

Ops

As appropriate


Monday, September 28, 2015



0700-0800

MPS validations

CTLS/Ops

Coordinate with RF group

0800-1000

BPLD validations

Bui


1000-2400

SR RF Conditioning w/ beam

Ops