Draft Schedule for Run02-1, 2017

May 23rd 0800 – May 31st 0800

Time

Descriptions

Studiers

SR Status


Monday, May 22, 2017(Pre-studies)



0900-1100

Prepare & store beam (MPS validation with beam)

OPS

Stored Beam & injection

1100-1300

HSCU Test Chamber Commissioning at low current (<25mA)

Yipeng Sun, Harkay, Emery

Stored Beam & injection

1300-2400

RF Conditioning with Beam

OPS

Stored Beam & injection

1300-2400

Measure tunes and recover lifetime at 5mA intervals (for HSCU Test chamber commissioning) (Actually started 21:15 on 5/22)

OPS

Stored Beam & injection


Tuesday, May 23



0000-1400

RF conditioning with beam (8 hours)

OPS

Stored Beam& Injection

0000-1400

Measure tunes and recover lifetime at 5mA intervals (for HSCU Test chamber commissioning)

OPS

Stored Beam & injection

1400-1500

Inject 324 singlets as part of HSCU Test chamber commissioning (102mA)

Harkay/Sun/Emery

Stored Beam & injection

1500-1900

BPLD validations

Hahne/Erwin

Stored Beam& Injection

1900-2200

X-ray BPM sanity check

Hahne

Stored Beam& Injection

2200-2400

Recover orbit

Xiao

Stored Beam & injection


Wednesday, May 24, 2017



0000-0300

Recover orbit

Xiao

Stored Beam & injection

0300-0700

CPU checkout (Xiao will leave instructions)

OPS

Stored Beam

0700-1000

ID4 aperature and impedance routine measurements

Emery

Stored beam & injection

1000-1200

workstation SR orbit sddscontrollaw with filters

Emery, Shang

Stored beam & injection

1300-1700

ID-7 aperture measurement

Yipeng Sun

Stored beam & injection

1700-2000

Test PAR streak camera operation in 1 Hz mode. Measure bunch length during accumulation

Harkay Calvey Lumpkin

Limited injection

1700-2200

RTFB/Datapool Unified feedback studies testing/software development

Sereno, et al

Stored beam & Injection


Thursday, May 25, 2017



0000-0200

RTFB/Datapool Unified feedback studies testing/software development

Sereno, et al

Stored beam & Injection

0200-0600

Check-out 24 bunch top-up and HSCU test chamber temps (before cooling clamp)

OPS

Stored beam & injection

0600-0830

Interleaving checkout

Yin-e Sun

No injection

0730-1230

Add cooling collar to 7ID HSCU test chamber downstream transition

MOM group

Zone A Access

0800-0900

Replace IR detector S38, Cav. 1 DS

Pace, McKenzie, Putnam

Zone F Access

0800-0900

Investigate Klixon on S38B:V3

Pace, McKenzie, Putnam, Puttkammer

Zone F Access

0830-1230

laser alignment

Dooling

Linac Access

1000-1100

SR RF waveguide switch

RF Group

No beam

1230-1330

Recover SR & injectors

OPS

Stored beam & injection

1400-1800

Check-out 24 bunch top-up and HSCU test chamber temps (after cooling clamp)

Harkay/OPS

Stored beam & injection

1800-2100

accumulation limit

Emery

Stored beam & injection

2100-2400

setup lower energy SR for Intrabeam scattering investigation

Emery

Stored beam & injection


Friday, May 26, 2017



0000-0400

IEX checkout (Xiao will leave instructions)

OPS

Stored beam & injection

0400-0600

Operator training (Linac)

OPS

No injection

0600-0800

OPEN



0800-1200

Investigate lifetime and injection efficiency

Yipeng Sun

Stored beam & injection

1200-1600

PAR high-charge studies vs RF params; measure bunch length (PD) and BPMs

Harkay Calvey Yao Dooling Berenc)

Stored beam & injection

1600-1900

Scan rf voltage in Booster at 6 GeV; measure fs

Harkay, Calvey, Yao

Stored beam & injection

1900-2100

Abort kicker check-out

Harkay

Stored beam & injection

2100-2400

Top-up Operations Check-out

OPS

Stored Beam & injection


Saturday, May 27, 2017



0000-0800

Top-up Operations Check-out (continued)

OPS

Stored Beam & Injection

0800-1200

6-ID GRID studies: system check out and calibration

Yang

Stored Beam & Injection

1200-1800

CPU Correction (if needed)

Xiao

Stored Beam & injection

1800-2400

Top-up Operations Check-out

OPS

Stored Beam & Injection


Sunday, May 28, 2017



0000-0800

Top-up Operations Check-out

OPS

Stored Beam & Injection

0800-1200

26-ID Compton XBPM studies: system check out and IOC program check out

Yang

Stored Beam & Injection

1200-1800

IEX Correction (if needed)

Xiao

Stored beam & injection

1800-2400

OPEN




Monday, May 29, 2017



0000-0800

OPEN



0800-1200

6-ID GRID studies: calibration and, possibly, feedback test.

Yang

Stored Beam & injection

1200-1600

PCG checkout with interleaving

Yin-e Sun

No injection

1600-1800

RG1 checkout

Yin-e sun

No injection

1800-2400

OPEN




Tuesday, May 30, 2017



0000-0700

OPEN



0700-1200

Final lattice set-up

Sajaev

Stored beam & injection

1200-1400

Response matrix measurement accuracy study

Sajaev

Stored beam & injection

1400-1700

Final orbit checkout

Xiao

Stored beam & injection

1400-1800

Pinhole camera & bunch puritycheckout/setup

Yang

Stored beam & injection

1800-2000

26-ID Compton XBPM studies: performance study

Yang

Stored beam & injection

2000-2400

OPEN




Wednesday, May 31, 2017



0000-0630

OPEN



0630-0800

Prepare for start of User Operations

Stored beam & injection

OPS