Machine Studies

Draft Schedule for Run02-3, 2017

June 12th 0800 - June 13th 0800



Time

Descriptions

Studiers

SR Status


Monday, June 12, 2017



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-0950

Investigate abort kicker timing (S39 flag and RF conditioning key insertion after this is complete)

Lenkzsus

No Beam

0930-1000

Reboot interleaving DSPs

PS Group/OPS

No Injection

0930-1000

replace the TC module in the PLC for RF5

Rf Group

No injection

0930-1030

Update LNDS PLC code

Smith

Stored Beam & Injection

0930-1130

Take output bridge current measurements

Vargas

No Beam

0930-1030

Shut down L5 and replace the leaking water hose

RF Group/ MOM Group

No injection

0930-1130

Swap sextupoles for upgrades

Ackley

No Beam

0930-1130

Upgrade 24V supply in L3 rack

Donkers

No Injection

1000-1100

Inspect S27 bellows

Gagliano

Access Zone D

1130-1200

Recover injectors/SR

OPS

Stored beam & injection

1200-1400

Test 1Hz PAR with 16 linac bunches. PAR beam only.

Yao, Lenkszus, Pietryla

No injection

1400-1500

test 1Hz Booster BPM operation

Yao, Pietryla

No injection

1500-1700

install and test modifications to the Linac modulator databases. (injection will be unavailable at end of studies)

Pietryla

Occassional injection

1500-1700

BPM testing

Sereno

Stored beam

1700-1900

BPLD validation script testing

Sereno/Shang

Stored beam & injection

1900-2300

PAR/booster high charge studies (1 Hz mode, no SR injection)

Calvey, Dooling, Berenc

No injection

2300-2400

response matrix accuracy study

Sajaev

Stored beam & injection


Tuesday, June 13, 2017



0000-0300

response matrix accuracy study (continued)

Sajaev

Stored beam & injection

0300-0700

OPEN



0700-0800

Prepare for User beam

OPS

Stored Beam & Injection