Machine Studies

Draft Schedule for Run02-2, 2017

June 5th 0800 - June 6th 0800



Time

Descriptions

Studiers

SR Status


Monday, June 05, 2017



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1130

Take output bridge current measurements

Vargas

No Beam

0930-1130

Swap sextupoles for upgrades

Ackley

No Beam

0930-1030

Replace MPC in sector 27 relay rack.

Martens

No Beam

1000-1100

Install temperature sensors

Erwin

Access Zone D

1000-1100

Check E-stop for S27-ID

Grimmer

Access Zone D

1000-1100

Linac console test

Smith/Pasky

No injection

1000-1100

increase the Current Gain in the Booster ramp converter B3C0H by 20% to 25%

Donkers

No Booster beam

1000-1300

Install MMS at S27

Blake

Access Zone D

1100-1200

Check connections for S27B:P0 and S28A:P0

Erwin

Access Zone D

1100-1300

PAR/Booster on-momentum injection study, requires change rf frequency,

Yao, Lenkszus

No Beam

1300-1330

Recover SR

OPS

Stored beam

1330-1500

Check the modulator HV connections on 1-4 (need to be off during check)

Rf Group

No injection

1500-1600

Test tune measurement

Shang

Stored beam

1600-1800

repeat some booster extraction bump characterization plus BTS

Emery

Occasional Injection

1600-1800

Investigate S27B:P0 & S28A:P0 and restore to OC if possible

Sereno

Stored beam

1800-2200

6 ID GRID calibration/feedback studies

Yang, Sereno

Stored beam & injection

2200-2400

26ID Compton XBPM studies

Yang, Sereno

Stored beam & injection


Tuesday, June 6, 2017



0000-0200

26ID Compton XBPM studies (continued)

Yang, Sereno

Stored beam & injection

0200-0600

Booster high-charge studies in the corrected orbit (1-Hz)

Harkay

Occasional injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection