Machine Studies

Schedule for Run02-7, 2012

July 9th 0800 - July 11th 0800



Time

Descriptions

Studiers

SR Status

 

Monday, July 9, 2012

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1130

SR waveguide switch to RF2 & RF3

RF Group

No beam

0930-1130

IEX testing

Deriy

No beam

0930-1330

replace bias card and upgrade firmware of S2 amplifiers

Yao, Gold, Vendor

No P0 feedback

0930-1030

Remove standard fan from S38-04 and re-install prototype fan and controls.

Erwin

No beam

0930-1330

investigate the loss of communications in the SR sector 2:3

Puttkammer

No beam

0930-1330

Investigate S10B:V2 readback errors

Puttkammer

No beam

0930-1330

Test S40AQ5 converter read backs,

Puttkammer

No beam

0930-1330

Replace cooling fans for the Canted Corrector power supplies (throughout the SR)

Puttkammer

No beam

0930-1330

Replace the DAC board for S26BV2

Puttkammer

No beam

0930-1600

Troubleshoot SR Tunnel AHU for Sectors 23/24

Kailus/Erwin

No impact

0930-1330

Pre-mount the hardware for the magnet interlocks for the Linac correctors

Hillman

No beam

1330-1400

13-ID End-to-End Test

Banks

No beam

1330-1400

install new clock signals for P0 feedback system. Need to power down iocsrfb

Scaminaci

No beam

1000-1200

Test rtfb iocs with no beam.

Xu Lenkszus

No beam

1400-1600

Retune S14 and S40 temperature control loops.

Putnam

Stored Beam & Injection

1600-2000

RHB lattice setup.

Xiao

Stored Beam & Injection

2000-2400

Orbit switch.

Xiao

Stored Beam & Injection

 

Tuesday, July 10, 2012

 

 

0000-0600

OPEN or BPM offset measurements.

OPS

Stored Beam & Injection

0600-1000

Coupling correction testing in 4NLSS-RHB.

Sajaev

Stored Beam & Injection

1000-1200

Test rtfb iocs with beam.

Xu Lenkszus

Stored Beam & Injection

1200-1400

Booster injection controllaw measurements.

Yao

Stored Beam & Injection

1400-1600

S19 vibration measurements setup test. Need shutter open.

OPS

Stored Beam & Injection

1600-2000

Measure various P0 feedback correlations.

Yao

Stored Beam & Injection

2000-2400

IEX commissioning.

Xiao

Stored Beam & Injection

 

Wednesday, July 11, 2012

 

 

0000-0300

IEX commissioning (continued).

Xiao

Stored Beam & Injection

0300-0630

OPEN or BPM offset measurements.

OPS

Stored Beam & Injection

0630-0800

Prepare for User beam

OPS

Stored Beam & Injection