Draft Schedule for Run02-11, 2012

August 7th 0800 – August 8th 0800



Time

Descriptions

Studiers

SR Status


Tuesday, August 7, 2012



0800-1000

Vibration studies w/ shutters open

OPS/FMS

Stored Beam & Injection

1000-1010

Collect XBPM orbit data

OPS

Stored Beam & Injection

1010-1130

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

1030-1230

Teng student studies (parasitic to gap scans 1st hr.)

Harkay

Stored Beam & Injection

1230-1430

Thermal image Zone B converters

Puttkammer

No Beam

1230-1430

Move external monitoring equipment

Wang

No Beam

1230-1430

Remove RF waveguide blanking plate

RF Group

No Beam

1230-1430

Test IOCconsole script

Pietryla

No impact

1230-1430

Replace noisy Bergoz NbBPM S6A:P1

Bui


1430-1500

Recover SR systems

OPS

Stored Beam & Injection

1500-1600

Measure BPM offset for S6A:P1

Xiao

Stored beam & injection

1600-1700

BPLD validation for 6-ID

Bui


1700-1900

Test several SR feedback IOC's upgrade with beam

S. Xu, Lenkszus

Stored beam & injection

1900-2200

measurements to check repeatability of optics measurement.

Wang, C

Stored beam & injection

2200-2400

Orbit Switch

Xiao

Stored beam & inj.


Wednesday, August 8, 2012



0000-0200

Orbit Switch (continued)

Xiao

Stored beam & inj.

0200-0630

IEX studies

Xiao

Stored beam & inj.

0630-0800

Prepare for User beam

OPS

Stored Beam & Injection