Machine Studies

Draft Schedule for Run02-1, 2012

May 23rd 0800 – May 30th 0800

Time

Descriptions

Studiers

SR Status


Wednesday, May 23, 2012



0800-0945

Continue Rf conditioning

OPS

Stored beam & inj.

0945-1200

Access to install new cooling clamps and turn on water to all installed clamps on S6 chamber

MOM group

Stored beam & inj

1200-2000

RF conditioning with beam

OPS

Stored beam & inj.

1400-1700

Preliminary BPM system checkout (parasitic only)

Decker

Stored beam & inj.

1400-1800

X-ray BPM checkout

canceled due to delay in conditioning

Hahne

Stored beam & inj.

1800-2400

Initial BPM system checkout

canceled due to delay in conditioning

Decker/Bui

Stored beam & inj.

2000-2400

BPLD validation.

Bui

Stored Beam & Injection


Thursday, May 24, 2012



0000-0800

24 singlets initial lattice setup.

Sajaev

Stored Beam & Injection

0800-1200

PSS shutter tests

SI Group

No Beam

0800-0815

Archive kicker waveforms

OPS

No beam

0800-1200

Switch pump 528 over to 527 for vibration testing. (PS to zero)

Theres

No beam

0815-1200

Install instrumentation to monitor IK1 & IK3

Hillman

No beam

0800-0900

RF waveguide switch to RF1&RF2 & MPS validation

RF Group/M. Smith

No beam

0900-1200

PSS end-to-end tests for 23 & 1

SI Group

No Beam

1200-1800

Orbit recovery.

Xiao

Stored Beam & Injection

1800-2400

Intermediate BPM system checkout.

Decker Hahne

Stored Beam & Injection


Friday, May 25, 2012



0000-0400

Coupling minimization using ORM. MOVED

Sajaev

Stored Beam & Injection

0400-0800

Injection studies. MOVED

Sajaev

Stored Beam & Injection

0800-1000

Zone A access to move SCU TC

Hoyt

Zone A access

0800-0830

fix/test a cable/fiber problem in SR sector 13 cabinet 2 correctors

Puttkammer

No beam

1000-1600

IEX correction coil measurements. CANCELED

Xiao

Stored Beam & Injection

1800-2200

X-ray BPM data collection. MOVED

Hahne Decker

Stored Beam & Injection

2200-2400

P1 BPM offset measurements (remote). CANCELED

Xiao Sajaev OPS

Stored Beam & Injection

0000-0800

Investigate injection/lifetime issues

Sajaev/Emery/Decker

Stored beam & injection

0800-2400

Access to investigate injection, replacement of S6 ID chamber

Multiple groups

No beam


Saturday, May 26, 2012



0000-0400

P1 BPM offset measurements (continued). CANCELED

Xiao Sajaev OPS

Stored Beam & Injection

0200-1000

OPEN



1000-1400

RHB lattice setup. CANCELED

Xiao

Stored Beam & Injection

1400-1700

P5 BPM offset measurements (remote). MOVED

Xiao OPS

Stored Beam & Injection

1700-2400

P2 BPM offset measurements (remote). MOVED

Xiao OPS

Stored Beam & Injection

0000-2400

S6 bake-out (bake-out started at 12:45)

MOM group

No beam


Sunday, May 27, 2012



0000-2400

S6 bake-out and post bake-out work

Multiple groups

No SR beam

0800-1200

Booster ORM measurements.

Yao

Injector beam

1200-1600

375 MeV injector setup


Injector beam

1200-1800

CPU checkout 1. MOVED

Xiao

Stored Beam & Injection

1800-2200

Top-up test run. MOVED

OPS

Stored Beam & Injection

2200-2400

6BM steering vs vacuum and temperature. CANCELED

Harkay Boon

Stored Beam & Injection


Monday, May 28, 2012



0000-0400

6BM steering vs vacuum and temperature (continued). CANCELED

Harkay Boon

Stored Beam & Injection

0300-0700

Orbit recovery

Xiao

Stored beam & injection

0700-1300

CPU checkout 1.

Xiao

Stored Beam & Injection

1300-1700

BPM studies

Decker

Stored Beam & Injection

1700-2100

Tune slopes with 24 singlets. CANCELED

Harkay Boon

Stored Beam & Injection

1700-2400

Top-up test run

OPS

Stored beam & injection


Tuesday, May 29, 2012



0000-0400

Injection studies

Sajaev

Stored Beam & Injection

0400-0800

Coupling minimization using ORM

Sajaev

Stored Beam & Injection

0800-1000

S35BM pinhole setup for user run.

Yang

Stored Beam & Injection

1000-1200

S35ID/S36AM bunch purity monitor setup for user run.

Yang

Stored Beam & Injection

1000-1200

SR closed-loop tune measurement test. CANCELED

Yao Shang

Stored Beam & Injection

1200-1600

Final BPM system checkout.

Decker Hahne

Stored Beam & Injection

1600-2400

CPU check #2

Xiao

Stored Beam & Injection


Wednesday, May 30, 2012



0000-0300

Hybrid lattice setup.

Sajaev

Stored Beam & Injection

0300-0600

Final lattice and injection setup.

Sajaev

Stored Beam & Injection

0600-0800

Prepare for user Operations (24 singlets – Top-Up)

Ops

Stored Beam & Injection