Machine Studies

Schedule for Run03-7, 2010

November 15th 0800 – November 17th 0800

Time

Descriptions

Studiers

SR Status


Monday, November 15, 2010



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0900

Gap Scans and update IDGapFF look-up tables

Schroeder/

OPS

Stored Beam & Injection

0900-0930

Set-up RF systems for high current

RF Group

No beam

0900-0930

Change MPS for 150mA study & disable gaps

Smith, M.

No beam

0930-1130

Set up 8RLSS lattice for high current studies

Sajaev

Stored beam & inj.

1130-1600

High current study

Harkay

Stored beam & inj.

1600-1630

Return RF to normal User operations

RF Group

No beam

1600-1630

Return MPS and ID gaps to normal User Operations

Smith, M.

No beam

1630-1700

Verify recovery to 102mA operations

Sajaev/Xiao

Stored beam & inj.

1700-2100

Set up RHB lattice

Sajaev/Xiao

Stored beam & inj.

2100-2400

Orbit Switch

Xiao

Stored beam & inj.


Tuesday, November 16, 2010



0000-0200

Orbit Switch

Xiao

Stored beam & inj.

0200-0630

Measure gas bremsstrahlung power in S35 while varying the beam current over its normal operating range (324 singlets)

Dooling/ Yang

Stored beam & inj.

0630-0900

Set-up PAR

Pasky/Smith T.

No injection

0800-1000

Modify MSL200 in iocs35bpm

Pietryla

No Beam

0900-1000

Replace SCDU card at S18A:P2. Will require rebooting IOCS17BPM

Keane

No Beam

0800-1100

Test prototype phase shifter at RF3

Horan

No Beam

0800-1100

Thermal scan Zone A & F converters

Puttkammer

No Beam

0900-1100

RG1 tests


No injection

1100-1200

Test SCR ramp with restore

Shang/ Schroeder

Stored beam

1200-1400

Test booster energy saving mode with Top-up

Yao, Shang

Stored beam & injection

1400-1700

Continue measure threshold of hybrids fill with reduced chromaticity with and without P0 feedback

Yao/ Sajaev

Stored beam & injection

1700-2300

Studies

Sajaev

Stored beam & inj.

2300-2400

BPM studies

Decker

Stored beam & inj.


Wednesday, November 17, 2010



0000-0630

BPM studies (continued)

Decker

Stored beam & inj.

0630-0800

Prepare for User beam

OPS

Stored Beam & Injection