Machine Studies

Draft Schedule for Run03-1, 2010

September 28th 0800 – October 5th 0800

Time

Descriptions

Studiers

SR Status


(Pre-Studies)

Monday, September 27, 2010



0900-1000

Set-up to store initial beam, MPS validation with beam



1000-2400

RF condition with beam to 115mA

OPS

Stored beam & injection

1600-2000

Initial pinhole camera setup >50mA (parasitic)

Yang

Stored beam


Tuesday, September 28, 2010



0000-0800

SR conditioning with Beam



0800-1200

BPLD validations (change MPS to 105mA before start)

Bui

Stored beam & inj.

1200-1600

Initial XBPM checkout

Hahne

Stored beam & occ. inj.

1200-1400

Check BESOCM noise from PAR septum

Yao, Donley

Occ. injection possible

1400-1800

Test Booster BM ramps

Yao

Occ. injection possible

1800-2400

OPEN




Wednesday, September 29, 2010



0000-0600

OPEN



0600-1200

Initial BPM checkout

Decker, Bui

Stored beam & inj.

1200-1800

S35 digial camera studies

Yang

Stored beam

1200-1300

Linac training

Schewe, Pasky

Limited injection

1300-1700

Test Soft current regulation on Booster BM

Yao, Wang, Shang

No injection

1800-2200

Initial Orbit recovery

Xiao

Stored beam & inj.

2200-2400

Correct beta functions for 24 singlets

Sajaev

Stored beam & inj.


Thursday, September 30, 2010



0000-0200

Initial Orbit recovery

Sajaev/Xiao

Stored beam & inj.

0200-0600

OPEN



0600-0800

Test changes to iocsrmon

DiMonte

No beam

0630-7:45

Troubleshoot a problem with starting pump 301 (P.S. and RF off)

Wright

No injection

0800-1200

Initial 29 Rogue Microwave studies

Decker, Lill

Stored beam & inj.

1200-1300

13-ID-C survey with 100mA (shutter permit needed)

Wyncott, Vacca

Stored beam

1300-1700

Test P0 feedback PEM and test system

Yao

Stored beam & inj.

1700-1900

Linac training (15:00-23:00)

Schewe

Limited injection

1900-2400

CPU Check-up

Xiao

Stored beam & inj.


Friday, October 01, 2010



0000-0100

CPU Check-up

Xiao

Stored beam & inj.

0100-0800

OPEN



0800-1000

Check Chain C summation signal for Zones A and F. 


Forrestal

No Beam

0800-1000

Measure CMPSI setpoint timing and polarity at S10A:H1

Fors

No beam

0800-1000

Replace damaged converter P2 cables in zone B

P.S. Group

No beam

0800-0830

Prepare for Zone A & Zone F access

OPS

No beam

0830-0930

Install lead shield and BLM detector at 5-ID BLM test area

Erwin/Yang

Access Zone A

0800-1200

RFG kicker validation

Shang

No Injection

0800-1200

PSS shutter checkouts

SI group

No Beam

0800-1200

Study Booster Dipole I & V ripple

Feng

Booster Access

0900-1100

Replace camera at BTS:FS5

Dombrowski/ Berg

Access Zone F

1200-1800

Final BPM system check-out (Top-up)

Decker

Stored beam & inj.

1800-2000

OPEN



2000-2400

Test new CPU software

Xiao

Stored beam & inj.


Saturday, October 02, 2010



000-0400

setup hybrid (return to standard 24 singlets after study)

Xiao

Stored beam & inj.

0400-2000

OPEN



2000-2400

Operational Top-UP check

OPS

Stored beam & inj.


Sunday, October 03, 2010



2400-0800

Operational Top-up check

OPS

Stored beam & inj.

0800-2200

open



2200-2400

Optimize injection and measure model

Sajaev

Stored beam & injection


Monday, October 04, 2010



0000-0200

Optimize injection and measure model

Sajaev

Stored beam & inj.

0200-0600

Continue testing APS lattice upgrade

Sajaev

Stored beam & inj.

0600-1000

repairs to Booster Pump contactor P- 301

MOM Group

No injection

0830-0900

IOCsrmon reboot

DiMonte

No impact

1000-1400

S29 Rogue Microwave studies

Lill

Stored beam & inj.

1400-1600

ID gap scans (top-up needed)

Schroeder

Stored beam & inj.

1600-1700

Position the UC/HEP circuit board

Dooling/HP

Access Zone F

1700-2300

Final S35 setup

Yang

Stored beam & inj.

2300-2400

Setup RHB

Xiao, Sajaev

Stored beam & inj


Tuesday, October 05, 2010



0000-0230

Setup RHB

Xiao, Sajaev

Stored beam & inj

0230-0630

Test failed sextupole correction

Sajaev

Stored beam & inj.

0630-0800

Prepare for user Operations (24 singlets – Top-Up)

Ops

Stored Beam & Injection