Machine Studies

Schedule for Run02-13, 2010

August 26th 0000 - August 26th 2400



Time

Descriptions

Studiers

SR Status


Thursday, August 26, 2010



0000-0700

Injection optimization of 8RLSS mock-up lattice

Sajaev

Stored Beam & Injection

0700-0900

Swap out S12B:Q4:PS

P.S. Group

No beam

0700-0800

Switch to RF Gun 1

Pasky

No injection

0700-1700

200mA study (0700-0900 -- No beam)

RF Group, Harkay, Sajaev, et al

Stored Beam & Injection

1700-2100

test new Booster ramp correction programs

Yao, Shang

Periodic Injection possible

2200-2400

Gentle shutdown of RF Systems and Power supplies

OPS

No beam