Machine Studies

Schedule for Run02-10, 2010

August 3rd 0800 – August 4th 0800



Time

Descriptions

Studiers

SR Status


Tuesday, August 03, 2010



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0900

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0900-1000

Replace S36 & 37 rack PS

Cours

No Beam

0900-1300

Thermal images Zones B & C PS

Puttkammer

No Beam

0900-1500

RF parallel studies

Horan

No Beam

0930-1500

Troubleshoot RF Gun1 and prepare it for bake-out


Linac Access

0930-1030

Replace rotary encoder at 3ID US

Grimmer

Access Zone A

0930-1100

IH survey

Flood

Access Zone F

1000-1130

IH survey

Flood

Access Zone A

1000-1300

IH survey

Flood

Access Injectors

1200-1600

booster ramping supply test

Yao/Hillman/ Puttkammer

Limited injection

1600-1800

Test ramp on/off in topup mode.

Yao/Shang

Stored beam & injection

1800-2200

Orbit variation study


Xiao

Stored beam & inj.

2200-2400

test new way of response matrix measurement

Sajaev

Stored beam & inj.


Wednesday, August 04, 2010



0000-0200

test new way of response matrix measurement

Sajaev

Stored beam & inj.

0200-0400

test new bpm gains.

Sajaev

Stored beam & inj.

0400-0700

IOCRF3HVPS reboot test

DiMonte/OPS

Stored beam & inj.

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection