Machine Studies

Schedule for Run01-12, 2010

April 20th 0800 – April 21st 0800



Time

Descriptions

Studiers

SR Status


Tuesday, April 20, 2010



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0910

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0910-0930

RF waveguide switch

Horan

No Beam

0910-1000

Replace fan at S:IK3

Puttkammer

No Beam

0930-1130

Remove upstream 1ID

Grimmer

Access Zone A

1130-1200

Recover SR systems

OPS

Stored Beam & Injection

1200-1300

Verify RF2 able to support beam and switch back to RF3

RF Group/Ops

Stored Beam & Inj.

1300-1400

SR Training

Pasky/Schroeder

Stored Beam & Inj.

1400-1600

Set-up new S23 RHB lattice

Xiao/Emery

Stored beam & inj.

1600-2200

Test S23 RHB lattice (shutters open)

S23 beamline personnel

Stored Beam & inj.

2200-2400

Switch lattice and recover orbit for 324 Singlets

Xiao/Sajeav

Stored Beam & inj.


Wednesday, April 21, 2010



0000-0230

Switch lattice and recover orbit for 324 Singlets

Xiao/Sajaev

Stored Beam & inj.

0230-0630

measure P0 feedback accumulation limit and damping time

Yao

Stored Beam & occ. inj.

0630-0800

Prepare for User beam (324 singlets)

OPS

Stored Beam & Injection