Draft Schedule for Run01-2, 2007

February 6th 0800 - February 7th 0800



Time

Descriptions

Studiers

SR Status


Tuesday, 2/6/07



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-1000

Install new ion pump controller @ RF3

RF group

RF group

0810-1000

Troubleshoot P3BMT1

Puttkammer

No Injection

0810-1000

Repair bad analog readbacks.

Puttkammer

No beam

0810-1000

Converter swapouts

Fors

No Beam

0810-1100

Replace L1 water pump motor

Ferry

No Injection

0830-0930

Repair 12ID gap limit switch.

Grimmer

Access Zone B

0830-0930

Reset xbpm limits on 17IDP2Y

Hahne

Access Zone C

0830-0930

Replace termination on DCCT test line

Pietryla

Access Zone F

1000-1030

PAR PEM testing

Yao

Limited injection

1030-1100

Restore SR beam.

OPS

Stored beam & injection

1100-1500

Linac beam study.

Pasky

Limited injection

1100-1500

S32 shielding verification.

Ramanathan

Stored beam & injection

1500-1600

Punch down S17 correctors.

Emery

Stored beam & injection

1500-1600

Test spare bunch current monitor. Parallel to punch down S17 correcotrs.

Varotto

Stored beam

1500-1900

Test linac controllaw. Parallel to everything.

Sereno

Injection possible always

1600-1800

Measure SR DCCT frequency spectrum with various fill patterns.

Pietryla

Stored beam & injection

1800-2000

Test single bunch feedback.

Yao

Stored beam & injection

2000-2200

Restore PAR orbit bump and optimize beam.

Yao

Limited injection

2000-2400

Xbpm alignment. First 2 hours parallel to PAR work.

Decker & lottery winner

Stored beam & injection


Wednesday, 2/7/07



0000-0200

Xbpm alignment (continued).

Decker & lottery winner

Stored beam & injection

0200-0700

Test all ID 10-m beta X lattice

Sajaev

Stored beam & injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection