Draft Schedule for Run01-1, 2007

January 23rd 0800 - January 30th 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 1/22/07

 

 

1100-2400

RF conditioning.

OPS

Stored beam & injection

1200-1600

SR bpm system shake down test (above 20 mA). Parallel to RF conditioning.

Singh Decker

Stored beam & injection

1600-1800

Initial pinhole cameras set up (above 50 mA). Parallel to RF conditioning.

Yang

Stored beam & injection

1800-2200

Mpbpm tests (above 20 mA). Parallel to RF conditioning.

Erwin Keane

Stored beam & injection

 

Tuesday, 1/23/07

 

 

0000-0700

RF conditioning.

OPS

Stored beam & injection

0700-0800

Switch to RF3 providing Booster.

Horan

No Beam

0800-1000

Operator training - Storage Ring

Poncin

Stored beam & injection

1000-1400

SR DC/AC orbit control/configuration tests.

Singh Lenkszus Shang

Stored beam & injection

1000-1100

Set up bunch current monitor. Parallel to bpm tests.

Varotto

Stored beam & injection

1400-1800

Orbit recovery.

Singh

Stored beam & injection

1800-2000

nb bpm test.

Sun

Stored beam & injection

2000-2400

Characterization and set up of 4-m pinhole camera for user run.

Yang

Stored beam & injection

 

Wednesday, 1/24/07

 

 

0000-0800

Measure P1 offsets, validate BPLDs.

Bui

Stored beam & injection

0800-1200

Test changes in RTFB and investigate beam losses from last run.

Lenkszus Emery Fors

Stored beam & injection

1200-1400

Operator training - Storage Ring.

Poncin

Stored beam & injection

1400-1600

BM xbpm tests.

Hahne

Stored beam & injection

1600-2000

Verify and set up PAR beam.

Yao

Limited injection

1600-2000

ID xbpm tests. Parallel to PAR beam setup.

Hahne

Limited injection

2000-2400

Correct beta functions.

Sajaev

Stored beam & injection

 

Thursday, 1/25/07

 

 

0000-0400

Check lifetime vs tunes.

Emery Sajaev

Stored beam & injection

0400-0800

OPEN

 

 

0800-1400

PSS validations

SI group

No beam

0800-1400

Laser Alignment PCgun tune measurement

Pasky

Access Linac

0800-0900

Switch to RF-3.

RF group

No Beam

1400-1500

Verify RF3 to Booster with beam and switch back to RF-5.

Horan

 

1500-1700

PEM testing with beam.

Schroeder

Stored beam & injection

1700-1900

Set up bunch purity measurement system.

Yang

Stored beam & injection

1900-2400

Final orbit recovery.

Singh

Stored beam & injection

 

Friday, 1/26/07

 

 

0000-0100

Final orbit recovery (continued).

Singh

Stored beam & injection

0100-0600

Create and test S8 RHB lattice.

Sajaev

Stored beam & injection

0600-1000

Check single bunch limits.

Sajaev Emery

Stored beam & injection

1000-1400

Linac beam studies.

Pasky

Limited injection

1000-1400

xbpm characterization for ID17, ID18, and ID24. Parallel to linac studies.

Decker

Stored beam & injection

1400-1800

Final orbit recovery with S8 RHB.

Singh

Stored beam & injection

1800-2000

Collect RTFB data.

Sun

Stored beam & injection

2000-2400

PAR bpm signal tests.

Yao Erwin

Stored beam & injection

 

Saturday, 1/27/07

 

 

0000-0600

Multibunch instability study.

Harkay

Stored beam & injection

0600-1000

OPEN

 

 

1000-1800

VW monitor tests.

Decker

Stored beam & injection

1800-2400

Power supply testing.

Fors

 

 

Sunday, 1/28/07

 

 

0000-1000

OPEN

 

 

1000-1400

Develop xbpm look up table.

Decker

Stored beam & injection

1400-1800

CPU correction.

Emery

Stored beam & injection

1800-2400

Verify topup operation.

OPS

Stored beam & injection

 

Monday, 1/29/07

 

 

0000-0600

Create all-ID RHB lattice (for impedance measurements).

Sajaev

Stored beam & injection

0600-0800

OPEN

 

 

0800-1200

HOM study.

Harkay Bromberek

Stored beam & injection

1200-1400

P0 feedback system drive test.

Yao

Stored beam & injection

1400-1800

Final operational orbit control configuration tests.

Singh Decker

Stored beam & injection

1800-2200

ID gap-corrector feedforward.

Emery

Stored beam & injection

2200-2400

mp bpm viewer with various bunch patterns.

Emery

Stored beam & injection

 

Tuesday, 1/30/07

 

 

0000-0200

mp bpm viewer with various bunch patterns (continued).

Emery

Stored beam & injection

0200-0600

Measure tune slope with single bunch.

Sajaev

Stored beam & injection

0600-0800

Ready for 0+24X1 fill pattern, low emittance, TopUp

OPS

Store Beam & Injection