Machine Studies

Schedule for Run03-8, 2004

November 23rd 0800 - November 23rd, 1600

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 11/23/04

 

 

0800-0805

Record XBPM data for user orbit with TopUp running

OPS

Stored Beam

0805-0830

Configure Linac with L4RF off

OPS

No Inj

0800-0830

Install HV power band pass filter on Harmonic Tube Amplifier #1 to test filter @ higher power (Amp #2 is one being used for operation/studies)

Smith

1st 0.5hrs no Inj

0805-0900

Troubleshoot ID35 FM2 DP circuit Replace transmitter if necessary (WRQ #16390

Swetin

No Beam

0805-1200

Replace seal on L4 water pump

Ferry

1st 0.5hrs no Inj

0805-0930

Repair a Gespac Analog readback card in Sector 40 cab 3.

Sprau/Vargas

No Beam

0805-0930

Replace a feedback card on the booster rf

Cherbak

No Inj

0805-1100

Bunch cleaning studies

Yao, Sereno, Grelick

1st 1.5hrs no Inj

1100-1300

Narrowband and X-ray bpm test with RTFB

Singh, Decker

Stored beam Occ. Inj.

1245-1300

Remove HV power band pass filter on PAR RF Harmonic Tube Amplifier #1

Smith

No Inj.

1245-1300

Reconfigure Linac with L4RF on

OPS

No Inj.

1300-1500

Bunch purity studies

Sereno

Stored Beam & Injection

1500-1600

Ready for 0+24X1 fill pattern, low emittance, TopUp

OPS

Stored Beam & Injection