Machine Studies

Schedule for Run02-09, 2004

July 19th, 0800 - July 21st, 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 7/19/04

 

 

0800-0805

Record XBPM data for user orbit with TopUp running

OPS

SR Beam

0805-0900

Waveguide switch from RF3/RF4 to RF2/RF4

RF Group

No Beam

0805-1000

Upgrade power supply for MPEOB strobe in Zone C

McNamara

No Beam

0805-1000

Swap out Corrector power supplies in Zone C for Reg upgrade

McNamara

No Beam

0805-1000

Install and test a fix for the A:H3 corrector problem

Lenkszus

No Beam

0805-0900

Reboot iocs40fb with a database that supports automated reflective memory testing

Lenkszus

No Beam

0805-1000

Test DACI software with SR PSCU

Hillman

No Beam

0805-1000

Test the K1 relay a potential external interlock problem with the Raws supplies starting in sector 6:7 and 36:37

Sprau

No Beam

0900-1200

Wireless testing Bldg. 420

Stejskal

No Impact?

0805-0900

Install TLD Badges in the LEUTL Tunnel on the Beam pipe

Vacca

No impact

0805-0900

Replace Gespac ADC board for the RF Gun Heater supply

Hillman

No Inj

0805-0930

Reboot linac iocs: ioclirfgun, ioclic1, ioclic4 to add pvs to monitor PS setpoint changes relative to conditioning

Varotto

No Inj

0830-1030

Test cables and replace Filter comparators at 10BP2, 15BP2, and 15BP3

Erwin

Access
Zone B

0830-0930

Reboot iocs3VP to incorporate vacuum pump database additions

Quock

No Beam

0830-1030

Terminate existing ACIS Cable and Power Cable for a future Radiation Monitor at the 26-ID Ratchet Door Column

Vacca, Forrestal

No Beam

0830-0930

Reboot iocfe31

M. Smith

No Beam

0830-0930

Replace red beacon at L1:MO:PF

Cours

No Inj

0830-0930

Replace rf source backup generator

Cherbak

No Beam

0830-1230

Replace the BOOSTER TO LEUTL radiation stop solenoid air manifold, verify the wiring of the ACIS limit switches, perform a `mini' validation of the affected ACIS

Markovich, Gagliano

Access
Booster (AA mode)

0830-1130

Replace burnt out magnet strobes lights

Hillman

Access
Booster

0830-1000

Bob Keithley to obtain measurements of BTX beamline for future ODR test station

Lumpkin

Access Booster

0845-1000

Check operation of PS2 at 18ID front end. Requires PSS validation of switches on PS2

Gagliano

Access
Zone C
(AA mode)

0930-1130

Operator Training - PAR(0700-1500)

Glenn, Jones

No Inj

0900-1000

Replace Rotary Encoder on upstream end of the 3IDds Insertion Device

Merritt

Access
Zone A

0900-1000

Reboot siocops (soft ioc) to load sequence program to automate testing of reflective memory.

Varotto

No Impact

0900-1000

Add bus analyzer board to sector 5 (iocs5vp) to collect data

Varotto

No Impact

0900-0930

Remove the VTM200 10/100Mb media converter undergoing field testing at iocs1bpm and restore connections to the Cabletron Ethernet media converter

Laird

No Beam

1000-1130

Test cable and replace Filter comparator at 35BP2

Erwin

Access
Zone E

1000-1030

Install cable in iocmtime racks to bring P0 to timing patch panel

Lenkszus

No Beam

1230-1300

Beam recovery.

OPS

Stored beam and injection

1300-1500

Reproduce Nan problem with controllaw.

Emery Lenkszus

Stored beam nad injection

1500-1600

CPU mode testing.

Smith Emery

Stored beam and injection

1600-1700

Test servo motor.

Stein Xu Sajaev

Stored beam and injection

1700-2100

Collect nbbpm spectrum. Parallel to RF phase...

Sun

Stored beam, no injection

1700-2100

RF phase anf timing jitter measurements in linac.

Borland

No injection

2100-2400

BPM tests.

Singh

Stored beam and injection

 

Tuesday, 7/20/04

 

 

0000-0600

Canted undulator xbpm studies.

Decker

Stored beam and injection

0600-0900

Prepare for 1296 bunches test.

Sereno Harkay Sajaev Decker et al.

Stored beam and injection

0900-1700

1296 bunch mode test with shutters open. Floor coordinator support required.

Randall

Stored beam and injection

1000-1200

Operator Training - Linac (0700-1500) can be concurrent to the User portion of 1296 bunch operation

Lesson, Jones

No injection

1700-2100

Bunch purity study.

Sereno Borland

Stored beam and injection

2100-2400

Bunch purity vs. number of bunches study.

Sereno

Stored beam and injection

 

Wednesday, 7/21/04

 

 

0000-0700

Xbpm alignment work.

Decker

Stored beam and injection

0100-0300

Operator Training - Booster. Parallel to xbpm alignment.

Forth

Limited Inj

0700-0800

Ready for 0+24X1 fill pattern, low emittance, TopUp

OPS

Stored beam and injection