Machine Studies

Schedule for Run02-04, 2004

June 15th, 0800 - 1600

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 6/15/04

 

 

0800-0805

Record XBPM data for user orbit with TopUp running

OPS

SR Beam

0805-1005

Operator Testing - Linac (08:00-15:00)

Pasky, Grodecki

No Inj

0805-1005

Replace the 18ID PS2 solenoid valve and rebuild the cylinder.

Gagliano

Access
Zone C

0805-1005

Swap out Corrector power supplies in S18 for Reg upgrade

McNamara

No Beam

0805-1005

Upgrade power supply for MPEOB strobe in S18-19

McNamara

No Beam

1005-1030

Recover the SR

OPS

Injection

1030-1100

Verify RTFB reboot PEM

CYao

Stored beam and injection

1100-1300

Software testing

Emery

Stored beam and injection

1300-1400

Beta function measurements

Sajaev

Stored beam and injection

1400-1530

Xbpm studies.

Decker

Stored beam and injection

1530-1600

Ready for 1+8X7 fill pattern, low emittance, TopUp

OPS