Machine Studies

Schedule for Run01-3, 2004

February 9th, 0800 - February 11th, 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 2/9/04

 

 

0800-0815

Record XBPM data for user orbit

OPS

SR Beam

0815-2400

Replace 1ID Fixed Mask

J. Gagliano

Zone-A
AA Mode

0830-0930

Install RMS motion diagnostics software on iocs40fb

F. Lenkszus

No Beam

0830-1230

Investigate EMW PS overcurrent trips; need to move gaps in Zone-B

B. Deriy

 

0900-1300

Repair RG2 Kicker

A. Hillman

Linac
Controlled Access

0900-1100

Redress cables at L2 DMU cabinet

Grelick/Yoder

 

0900-1100

Plug RG1 & RG2 Heater PSs into normal AC power.

A. Hillman

 

0900-1100

Install Diodes on P:SD & P:Q4 PSs

R. Seglem

 

0900-1200

Replace 3ID & 4ID Dosimeters

M. Petra

Zone-A
AA Mode

0900-1000

Reboot iocleutl1 & iocbsynclight

J. Stevens

 

0930-1730

Replace 2 linear stages for new S35 pinhole slits

BingXin Yang

Zone-E
AA Mode

0930-1430

Check cylinder operation 34ID PS1 & PS2

J. Gagliano

Zone-E
AA Mode

0930-1330

Investigate S24C:BM Klixon problem

P. McNamara

Zone-D
AA Mode

0930-1030

Check interlock equipment locations and spacing at 23ID front end. No components will be disconnected.

J. Forrestal

Zone-D
AA Mode

1000-1200

Check coax pins @ 17BM P2 Xbpm check repair potentiometer @ 18ID P1 Xbpm

M. Hahne

Zone C
AA Mode

1000-1100

Remove experiment from Booster tunnel

Kevin Dolan/OPS

Booster

Controlled Access

1000-1100

Reboot iocbvp1, iocbvp3 & iocrfgun

M. Varotto

 

1000-1100

Install VME bus analyzer in iocs25fb which will be power cycled.

F. Lenkszus

 

1100-1200

Verify Thermocouples at S:IK2 & S:IK3

C. Putnam

Controlled Access F

1100-1200

Adjust illumination control BTS flag #6

B. Berg

Controlled Access F

1100-1200

Check 40AP4 button, cables and matching networks, using network analyzer.

L. Erwin

Controlled Access F

1230-1630

Testing and optimization of RF2's regulation system

Nassiri/Trento

No Beam

1300-1500

Validate RG2 Kicker

Pasky/Lewellen

 

1500-1700

Linac tuning

Pasky/Lewellen

 

1700-2400

Booster direct injection controlLaw studies

N. Sereno

 

 

Tuesday, 2/10/04

 

 

0000-2400

Replace 1ID Fixed Mask

J. Gagliano

Zone-A
AA Mode

0000-0100

Booster direct injection controlLaw studies

N. Sereno

 

0100-0400

PAR Operator training

Klimowych

 

0700-0900

Linac Operator training

C. Forth

 

0700-1100

Investigate S23A:V2:PS readback problem

P. McNamara

No Beam

0900-1200

Testing and optimization of RF2's regulation system

Nassiri/Trento

No Beam

0900-1700

Linac & LEUTL PEM testing

M. Borland

 

1300-1430

Reposition SR IK2 vacuum chamber thermocouples. Remove 8 thermocouples and reposition the in the correct position

C. Putnam

Controlled Access F

1300-1430

Adjust illumination control BTS flag #6

B. Berg

Controlled Access F

 

Wednesday, 2/11/04

 

 

0000-0700

SR recovery and Lattice setup

Emery, Borland, Sajaev

 

0700-0800

Ready for 0+24X1 fill pattern, low emittance, TopUp

OPS

Stored beam and injection