| ECR # |
Date |
Responsible Engineer |
Risk Level |
Location |
Description |
Status |
| SI-0001 |
4/8/2005 |
Dawson |
Medium |
12ID |
Add DI water monitoring |
Approved |
| SI-0002 |
4/8/2005 |
Friedman |
High |
12ID |
Enable non-mono mode operation of P4-B shutter |
Approved |
| SI-0003 |
4/8/2005 |
Friedman |
Medium |
15ID |
Correct wiring in station C 15 U |
Approved |
| SI-0004 |
4/8/2005 |
Hawkins |
High |
30ID |
Add integral shutter code |
Approved |
| SI-0005 |
4/8/2005 |
Hawkins |
High |
30ID |
Review new beamline shutter control for G3 systems |
Approved |
| SI-0006 |
4/8/2005 |
Hogrefe |
Low |
ACIS Inj |
Table 0 NSV relay mods. |
Complete |
| SI-0007 |
4/8/2005 |
Hogrefe |
High |
ACIS RF |
3-5 switch mods |
Complete |
| SI-0008 |
4/8/2005 |
Hogrefe |
Low |
ACIS L/P |
Incorporate Chain C Bypass |
Complete |
| SI-0009 |
4/8/2005 |
Dawson |
Low |
SR |
Develop portable test fixture for the SR abort chassis |
|
| SI-0010 |
4/8/2005 |
Dawson |
Medium |
SR |
Develop new code for the SR abort chassis |
|
| SI-0011 |
4/8/2005 |
Belcher |
Medium |
Beamlines |
Replace LOVE controllers with new design |
In Progress |
| SI-0012 |
4/8/2005 |
Dawson |
Low |
Beamlines |
Ground upper user control panels |
Approved |
| SI-0013 |
4/8/2005 |
Belcher |
Medium |
Beamlines G3 |
Add Local Shutter control to G3 beamlines |
Approved |
| SI-0014 |
4/8/2005 |
McNamara |
Low |
FEEPS |
Upgrade Version 3 systems |
Approved |
| SI-0015 |
4/12/2005 |
Emerson |
Medium |
Beamlines G3 |
Change cross trip and faults present to pulsed signals |
Dis-Approved |
| SI-0016 |
7/18/2005 |
Hawkins |
NA |
30ID |
Design BLEP System |
Approved |
| SI-0017 |
7/18/2005 |
Hogrefe |
Medium |
ACIS RF |
Remove the Zone F/RF Test room chassis |
Approved |
| SI-0018 |
7/18/2005 |
Hogrefe |
Medium |
ACIS RF |
Implement ACIS portion of 3/5 switch |
Approved |
| SI-0019 |
7/18/2005 |
Hogrefe |
Low |
ACIS SR |
Add PLC input to monitor S39 view screen Chain C status |
Approved |
| SI-0020 |
7/18/2005 |
Hogrefe |
Low |
ACIS SR |
Replace RF Cond and Dipole test keys |
Approved |
| SI-0021 |
7/18/2005 |
Hogrefe |
Low |
ACIS RF |
Modify RF Test room W.G. shutter interface |
Approved |
| SI-0022 |
7/18/2005 |
Forrestal |
Medium |
Beamlines |
Implement new MEZZIE design |
Approved |
| SI-0023 |
7/18/2005 |
Forrestal |
Medium |
ACIS SR |
Implement delayed tripping of rad monitors |
Approved |
| SI-0024 |
7/19/2005 |
McNamara |
Low |
FEEPS |
Replace LOVE controllers with analog modules |
Approved |
| SI-0025 |
7/19/2005 |
McNamara |
Low |
FEEPS |
Remove DP and old UPS interlocks from code |
Approved |
| SI-0026 |
7/22/2005 |
Belcher |
Medium |
Beamlines |
Gen 1 BLSIE Design |
|
| SI-0027 |
8/5/2005 |
Emerson |
Medium |
Beamlines |
Door Pneumatic Box Upgrade |
Approved |
| SI-0028 |
8/5/2005 |
Hogrefe |
Medium |
ACIS |
Lock door in CA Mode in Zone F |
Dis-Approved |
| SI-0029 |
8/5/2005 |
Hogrefe |
Medium |
ACIS |
Lock door in CA Mode in SR |
Dis-Approved |
| SI-0030 |
8/5/2005 |
Friedman |
Low |
BLEPS |
4ID Take P4-39 out of PLC code |
Approved |
| SI-0031 |
8/5/2005 |
Dawson |
Medium |
PSS |
2ID Remove Station C User Panel |
Approved |
| SI-0032 |
8/5/2005 |
Friedman |
Medium |
BLEPS |
8ID remove O/C PB for P8-E |
Approved |
| SI-0033 |
8/5/2005 |
Friedman |
Medium |
PSS |
26ID Integrate BLS-C and BLS-C shutters |
Approved |
| SI-0034 |
8/5/2005 |
Friedman |
Medium |
PSS |
32ID Integrate DIW for Pink Beam Stop |
Approved |
| SI-0035 |
8/5/2005 |
Friedman |
Medium |
PSS |
12ID Enable operation of P4-B |
Approved |
| SI-0036 |
8/5/2005 |
Friedman |
Low |
BLEPS |
17BM remove GV2 and add DIW for Be window |
Approved |
| SI-0037 |
8/24/2005 |
Hogrefe |
Low |
ACIS |
AA trip, CA mode keys secure, door open |
Approved |
| SI-0038 |
8/24/2005 |
Friedman |
None |
Beamlines |
Implement RSI |
Approved |
| SI-0039 |
8/24/2005 |
Friedman |
None |
Beamlines |
8ID BLEPS upgrade |
Approved |
| SI-0040 |
11/8/2005 |
Servino |
None |
G3 |
Use Panelview for G3 IO validations |
|
| SI-0041 |
1/18/2006 |
Fagen |
None |
Beamlines |
Changes to 17BM BLEEPS |
Approved |
| SI-0042 |
1/23/2006 |
Mcnamara |
None |
FEEPS |
26ID Remove Be Window from FEEPS code |
Approved |
| SI-0043 |
1/30/2006 |
Nguyen |
Low |
PSS |
26ID Station C door permit |
Approved |
| SI-0044 |
2/23/2006 |
Forrestal |
Low |
ACIS |
Lock Tunnel Access without a key |
Approved |
| SI-0045 |
2/23/2006 |
Forrestal |
Low |
ACIS |
Sync Exclusion Gate Trip to LINAC ACIS |
Approved |
| SI-0046 |
2/23/2006 |
Forrestal |
Low |
ACIS |
Eliminate ACIS Chain C's |
|
| SI-0047 |
2/23/2006 |
Forrestal |
Low |
ACIS |
Remove LTP Tripple Stop from the BESCOM logic |
Approved |
| SI-0048 |
4/5/2006 |
Banks |
High |
Beamlines |
Change the P6-B shutter into a mono mode only shutter |
Approved |
| SI-0049 |
4/5/2006 |
Friedman |
Medium |
Beamlines |
23ID - Rev Search Path and partition Sta B&D into 2 zones |
Approved |
| SI-0050 |
5/24/2006 |
Banks |
High |
Beamlines |
12BM - Make all necessary changes to oper. in Mono Mode Only |
Approved |
| SI-0051 |
6/7/2006 |
Nguyen |
High |
Beamlines |
2BM - Remove BLS-B from PSS code (leaky shutter) |
Approved |
| SI-0052 |
6/7/2006 |
Fagan |
Medium |
PSS |
Ring Dump Cross trip |
|
| SI-0053 |
6/14/2006 |
Servino |
Medium |
G3 |
Remove FEEPS shutter permit from ESD-A and ESD-B |
|
| SI-0054 |
7/12/2006 |
McNamara |
Low |
PSS |
Add Key switch to bypass FEEPS/BLEPS 4 End to End Test |
Approved |
| SI-0055 |
8/4/2006 |
Fagan |
Low |
BLEPS |
17BM BLEPS misc changes |
Approved |
| SI-0056 |
8/25/2006 |
Hogrefe |
Medium |
ACIS |
Remove Chain C from RF and SR |
Approved |
| SI-0057 |
8/26/2006 |
Hogrefe |
Low |
ACIS |
Provide ACIS status to PSG to kill strobe in ITS |
Approved |
| SI-0058 |
10/16/2006 |
Friedman |
High |
Beamlines |
Install new door at 17BM-B |
Approved |
| SI-0059 |
|
|
|
|
|
|
| SI-0060 |
|
|
|
|
|
|
| SI-0061 |
|
|
|
|
|
|
| SI-0062 |
|
|
|
|
|
|
| SI-0063 |
|
|
|
|
|
|
| SI-0064 |
|
|
|
|
|
|