August  / September Shutdown
  QUALITY T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
JOB DESCRIPTION REQ # ENGINEER AUDIT TECHNICIANS 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
LINAC                                                                              
Bakeout L5 sled 24232 Hoyt Mark Wayne, Cheri w w w w w w                                                          
Maintenance vac cabinets 24233 Hoyt Mark Wayne, Cheri                           w w w       w w w w                        
                                       
PAR                                                                              
Maintenance vac cabinets 24234 Hoyt Mark Wayne, Cheri                           w w w       w w w w                        
                                                                               
BOOSTER                                                                              
Maintenance vac cabinets 24235 Hoyt Mark Wayne, Cheri                           w w w       w w w w     w w w w w          
               
STORAGE RING Zones A -E                                                                            
Maintenance vac cabinets 24238 Try Hoyt Bob, CJ                               w       w w w w           w w     w w  
Installl new pneumatics 12ID 24237 Try Mark Bob, CJ                                                   12 12 w              
Install XBPM, FEV sector 13ID 24236 Try Hoyt Wayne, Cheri           w w w w     w w w                                          
     
STORAGE RING Zone F                                                                              
Replace coupler RF 40-2 24239 Mark Try Bob, CJ w w     w w w w                                         w w          
Leak check all RF turbo systems 24240 Mark Try Bob, CJ               w w     w w w w w                                      
Maintenance vac cabinets 24241 Mark Try Bob, CJ                               w       w w w w                        
                                                                               
LEUTL                                                                              
                                                                               
CLOSE STORAGE RING AND FRONT END VALVES  7:00 A.M. 9/14/08 Bob, CJ
Guy, Aaron, Raul, Paul LCLS, NSLSII